Pipeline RFPs
Search pipeline RFP opportunities from state pipeline safety agencies, utility commissions, and energy departments. Find solicitations for pipeline construction, maintenance, and pipeline safety services updated daily.
Includes providing and installing 8,909 LF of water line of which 472 LF to be installed by Jack & Bore in 36" steel casing pipe and 8,437 LF to be installed by open cut, gate valves, fittings, fire hydrants, air release valves, blowoff assemblies, concrete pavement replacements, hydrostatic pressure testing, disinfection, bacteriological testing, storm water pollution prevention, clearing and grubbing, maintenance of traffic, cleaning, planting, restoration, ancillary related work.
Posted Date
Feb 19, 2026
Due Date
Jun 3, 2026
State Hwy 31 Pipeline & Ground Storage Tank Contract 1-Pipeline (RFB)
Release: Feb 19, 2026
Close: Jun 3, 2026
Includes providing and installing 8,909 LF of water line of which 472 LF to be installed by Jack & Bore in 36" steel casing pipe and 8,437 LF to be installed by open cut, gate valves, fittings, fire hydrants, air release valves, blowoff assemblies, concrete pavement replacements, hydrostatic pressure testing, disinfection, bacteriological testing, storm water pollution prevention, clearing and grubbing, maintenance of traffic, cleaning, planting, restoration, ancillary related work.
AvailableBRINE PIPELINE ACCESS IMPROVEMENTS
AvailableThe Brine Pipeline Access Improvements project involves various maintenance access and pipeline isolation improvements along the existing Brine Discharge Pipeline. The work includes the installation of pipeline/access improvements along Goetz Road, Winter Circle, Salt Creek channel, and within the Salt Creek Trail, as well as cleaning of approximately 13,140 linear feet of the existing Brine Discharge Pipeline. The project is located in the City of Menifee, Riverside County, California, and is a Small Business Set Aside acquisition conducted under Federal Acquisition Regulation (FAR) Part 14 Sealed Bid.
Posted Date
Dec 29, 2025
Due Date
Dec 29, 2026
BRINE PIPELINE ACCESS IMPROVEMENTS
Release: Dec 29, 2025
Close: Dec 29, 2026
The Brine Pipeline Access Improvements project involves various maintenance access and pipeline isolation improvements along the existing Brine Discharge Pipeline. The work includes the installation of pipeline/access improvements along Goetz Road, Winter Circle, Salt Creek channel, and within the Salt Creek Trail, as well as cleaning of approximately 13,140 linear feet of the existing Brine Discharge Pipeline. The project is located in the City of Menifee, Riverside County, California, and is a Small Business Set Aside acquisition conducted under Federal Acquisition Regulation (FAR) Part 14 Sealed Bid.
AvailableBrine Pipeline Access Improvements
AvailableThe work includes various maintenance access and pipeline isolation improvements along the existing Brine Discharge Pipeline (16" to 30" diameters). Construction generally includes the installation of 4 pipeline/access improvements along Goetz Road, 2 pipeline/access improvements along Winter Circle, 4 pipeline/access improvements along the Salt Creek channel and within the Salt Creek Trail, and 2 pipeline/access improvements located inside the District's Sun City Regional Water Reclamation Facility property. The work also includes cleaning of approx. 13,140 LF of the existing Brine Discharge Pipeline.
Posted Date
Dec 29, 2025
Due Date
May 13, 2026
Brine Pipeline Access Improvements
Release: Dec 29, 2025
Close: May 13, 2026
The work includes various maintenance access and pipeline isolation improvements along the existing Brine Discharge Pipeline (16" to 30" diameters). Construction generally includes the installation of 4 pipeline/access improvements along Goetz Road, 2 pipeline/access improvements along Winter Circle, 4 pipeline/access improvements along the Salt Creek channel and within the Salt Creek Trail, and 2 pipeline/access improvements located inside the District's Sun City Regional Water Reclamation Facility property. The work also includes cleaning of approx. 13,140 LF of the existing Brine Discharge Pipeline.
AvailableLandfill Gas Pipeline Realignment
AvailableWorks include approx. 1 LS Clear and Grub Site; 1,490 LF of Erosion/Sediment Control - Silt Fence; 830 LF of 8" HDPE Pipe with Earthen Backfill; 910 LF of Abandon Existing 8" HDPE Pipe (removal); 5,600 SY Seeding/Fertilizing/Mulching.
Posted Date
Apr 1, 2026
Due Date
Apr 22, 2026
Landfill Gas Pipeline Realignment
Release: Apr 1, 2026
Close: Apr 22, 2026
Works include approx. 1 LS Clear and Grub Site; 1,490 LF of Erosion/Sediment Control - Silt Fence; 830 LF of 8" HDPE Pipe with Earthen Backfill; 910 LF of Abandon Existing 8" HDPE Pipe (removal); 5,600 SY Seeding/Fertilizing/Mulching.
AvailableCleaning and inspection of sanitary sewers, manholes, and appurtenances, that include acoustic inspections, televising, cleaning with grease treatment where necessary, manhole locating and television inspection QA/QC review.
Posted Date
Mar 30, 2026
Due Date
May 6, 2026
Pipeline Assessment and Maintenance - Citywide
Release: Mar 30, 2026
Close: May 6, 2026
Cleaning and inspection of sanitary sewers, manholes, and appurtenances, that include acoustic inspections, televising, cleaning with grease treatment where necessary, manhole locating and television inspection QA/QC review.
AvailablePipeline Assessment and Maintenance - Citywide. Principal items of work for this contract include, but are not limited to: Cleaning and inspection of sanitary sewers, manholes, and appurtenances, that include acoustic inspections, televising, cleaning with grease treatment where necessary, manhole locating and television inspection QA/QC review.
Posted Date
Mar 25, 2026
Due Date
May 6, 2026
Pipeline Assessment and Maintenance-Citywide
Release: Mar 25, 2026
Close: May 6, 2026
Pipeline Assessment and Maintenance - Citywide. Principal items of work for this contract include, but are not limited to: Cleaning and inspection of sanitary sewers, manholes, and appurtenances, that include acoustic inspections, televising, cleaning with grease treatment where necessary, manhole locating and television inspection QA/QC review.
AvailableFY26 Pipeline Dredging MATOC
AvailableThe U.S. Army Corps of Engineers, Galveston District is soliciting proposals for an Indefinite Delivery/Indefinite Quantity (IDIQ) Multiple Award Task Order Contract (MATOC) for pipeline dredging services. The contract will cover multiple locations within the boundaries of the Galveston District to maintain dredging facilities. Interested parties must access the full solicitation package through the PIEE Solicitation Module as indicated in the official notice.
Posted Date
Apr 14, 2026
Due Date
May 13, 2026
FY26 Pipeline Dredging MATOC
Release: Apr 14, 2026
Close: May 13, 2026
The U.S. Army Corps of Engineers, Galveston District is soliciting proposals for an Indefinite Delivery/Indefinite Quantity (IDIQ) Multiple Award Task Order Contract (MATOC) for pipeline dredging services. The contract will cover multiple locations within the boundaries of the Galveston District to maintain dredging facilities. Interested parties must access the full solicitation package through the PIEE Solicitation Module as indicated in the official notice.
AvailableNGWSP BLOCK 2-3 PIPELINE
AvailableThe U.S. Bureau of Reclamation, Upper Colorado Basin Region issued a presolicitation for the Navajo-Gallup Water Supply Project (NGWSP) Block 2-3 Pipeline to construct buried water transmission pipelines and storage tanks. This full and open procurement has an estimated value between $100,000,000 and $150,000,000 and is expected to be a fixed-price contract. The project includes the construction of SCADA systems and associated works with a response deadline set for June 2026.
Posted Date
Mar 10, 2026
Due Date
Jun 24, 2026
NGWSP BLOCK 2-3 PIPELINE
Release: Mar 10, 2026
Close: Jun 24, 2026
The U.S. Bureau of Reclamation, Upper Colorado Basin Region issued a presolicitation for the Navajo-Gallup Water Supply Project (NGWSP) Block 2-3 Pipeline to construct buried water transmission pipelines and storage tanks. This full and open procurement has an estimated value between $100,000,000 and $150,000,000 and is expected to be a fixed-price contract. The project includes the construction of SCADA systems and associated works with a response deadline set for June 2026.
AvailableNGWSP Block 2-3 Pipeline
AvailableApprox. 6.0 miles of 42" diameter buried water transmission pipe. Approx. 5.9 miles of 48" diameter buried water transmission pipe. Two 0.3 million-gallon ground level storage tanks, yard, and access road. Wash crossings. Bored crossings. Precast manhole structures. Concrete thrust collars, tapers, and encased miter bends. Buried manholes. Valves, air valves, and blowoffs. Road crossings. Utility crossings. Erosion control. Cathodic protection. Supervisory Control and Data Acquisition (SCADA) equipment and fiber optic cabling.
Posted Date
Dec 18, 2025
Due Date
Jun 30, 2026
NGWSP Block 2-3 Pipeline
Release: Dec 18, 2025
Close: Jun 30, 2026
Approx. 6.0 miles of 42" diameter buried water transmission pipe. Approx. 5.9 miles of 48" diameter buried water transmission pipe. Two 0.3 million-gallon ground level storage tanks, yard, and access road. Wash crossings. Bored crossings. Precast manhole structures. Concrete thrust collars, tapers, and encased miter bends. Buried manholes. Valves, air valves, and blowoffs. Road crossings. Utility crossings. Erosion control. Cathodic protection. Supervisory Control and Data Acquisition (SCADA) equipment and fiber optic cabling.
AvailableRosedale PHMSA Grant Pipeline Rehab
AvailableWork includes traffic control, 1,791 LF of 2" pe gas line; cip, 2,030 LF of 3/4" pe gas service line, 1 EA of 2" pe valve; cip, 505 SY of asphalt patch; cip, 505 SY of remove & dispose of asphalt; compl, 6,233 SY of pavement microsurfacing; cip, 1,797 LF of curb & gutter (stnd), all types; cip, 640 sf of sidewalk, 4" thick; cip, 1 SF of ada ramp, 6" thick, 2 EA of tree trimming. See attached file.
Posted Date
Mar 27, 2026
Due Date
May 7, 2026
Rosedale PHMSA Grant Pipeline Rehab
Release: Mar 27, 2026
Close: May 7, 2026
Work includes traffic control, 1,791 LF of 2" pe gas line; cip, 2,030 LF of 3/4" pe gas service line, 1 EA of 2" pe valve; cip, 505 SY of asphalt patch; cip, 505 SY of remove & dispose of asphalt; compl, 6,233 SY of pavement microsurfacing; cip, 1,797 LF of curb & gutter (stnd), all types; cip, 640 sf of sidewalk, 4" thick; cip, 1 SF of ada ramp, 6" thick, 2 EA of tree trimming. See attached file.
AvailableJohnston Road 16" Pipeline Project
AvailableConstruct approx. 2,900 LF of District Furnished 16" diameter Ductile Iron Pipe (DIP) water main; relocate existing water main with approx. 260 LF of existing 10" Asbestos Cement Pipe (ACP) with new 8" diameter Polyvinyl Chloride (PVC) pipe water main; install butterfly and gate valves; air vacuum release assemblies; blow off assemblies; fire hydrant assemblies; asphalt concrete pavement restoration; concrete pavement restoration; dispose of piping and fittings.
Posted Date
Mar 17, 2026
Due Date
Apr 21, 2026
Johnston Road 16" Pipeline Project
Release: Mar 17, 2026
Close: Apr 21, 2026
Construct approx. 2,900 LF of District Furnished 16" diameter Ductile Iron Pipe (DIP) water main; relocate existing water main with approx. 260 LF of existing 10" Asbestos Cement Pipe (ACP) with new 8" diameter Polyvinyl Chloride (PVC) pipe water main; install butterfly and gate valves; air vacuum release assemblies; blow off assemblies; fire hydrant assemblies; asphalt concrete pavement restoration; concrete pavement restoration; dispose of piping and fittings.
AvailableThis RFB from the City of Hurst involves the complete reconstruction of Pipeline Road from Harrison Lane to Brown Trail, including concrete pavement, waterlines, and sanitary sewers. The project scope also encompasses storm sewer construction, bridge demolition and reconstruction, street lighting, traffic signals, and landscape restoration. Bids for this $15,000,000 to $30,000,000 project are due by April 29, 2026, with a virtual bid opening scheduled for the same day.
Posted Date
Mar 26, 2026
Due Date
Apr 29, 2026
West Pipeline Road Improvements, Phase 4
Release: Mar 26, 2026
Close: Apr 29, 2026
This RFB from the City of Hurst involves the complete reconstruction of Pipeline Road from Harrison Lane to Brown Trail, including concrete pavement, waterlines, and sanitary sewers. The project scope also encompasses storm sewer construction, bridge demolition and reconstruction, street lighting, traffic signals, and landscape restoration. Bids for this $15,000,000 to $30,000,000 project are due by April 29, 2026, with a virtual bid opening scheduled for the same day.
AvailableInstallation of approximately 14,300 linear feet of 96-inch steel water pipe, 570 linear feet of 78-inch steel water pipe, and 30 linear feet of 54-inch prestressed concrete cylinder water pipe by a combination of open cut and tunneling methods in addition to cathodic protection, electrical, instrumentation and controls for electrically actuated valves, site and paving restoration and all appurtenances.
Posted Date
Mar 11, 2026
Due Date
May 8, 2026
Southwest 96" Water Transmission Pipeline Project
Release: Mar 11, 2026
Close: May 8, 2026
Installation of approximately 14,300 linear feet of 96-inch steel water pipe, 570 linear feet of 78-inch steel water pipe, and 30 linear feet of 54-inch prestressed concrete cylinder water pipe by a combination of open cut and tunneling methods in addition to cathodic protection, electrical, instrumentation and controls for electrically actuated valves, site and paving restoration and all appurtenances.
AvailableThe work consists of the installation of approx 1. 2 miles (6,300 LF) of 30" and 24" pvc pipe, additionally, the work includes a 16" and 12-inch pvc pipe. Work will also include the installation of all necessary valving along the transmission line and several trenchless crossings under roadways. See attached file.
Posted Date
Mar 16, 2026
Due Date
Apr 23, 2026
FM 1626 Transmission Main Pipeline (RFP)
Release: Mar 16, 2026
Close: Apr 23, 2026
The work consists of the installation of approx 1. 2 miles (6,300 LF) of 30" and 24" pvc pipe, additionally, the work includes a 16" and 12-inch pvc pipe. Work will also include the installation of all necessary valving along the transmission line and several trenchless crossings under roadways. See attached file.
AvailableOn-call contract to provide closed-circuit television (CCTV) inspection, pipeline and structure cleaning, debris and sediment removal, lateral inspection and cleaning, and related support services for the district's wastewater conveyance system, including the metropolitan interceptor sewer (MIS) system, associated collection and interceptor sewers, manholes and other structures, and water reclamation facilities.
Posted Date
Apr 13, 2026
Due Date
May 12, 2026
On-Call CCTV Inspection and Pipeline Cleaning Services
Release: Apr 13, 2026
Close: May 12, 2026
On-call contract to provide closed-circuit television (CCTV) inspection, pipeline and structure cleaning, debris and sediment removal, lateral inspection and cleaning, and related support services for the district's wastewater conveyance system, including the metropolitan interceptor sewer (MIS) system, associated collection and interceptor sewers, manholes and other structures, and water reclamation facilities.
AvailableProcure new and replacement color video pipeline inspection systems, sewer cleaning units, OEM-certified accessories, and maintenance support. These resources are needed to support sewer line inspection, cleaning, and overall infrastructure asset management operations.
Posted Date
Apr 8, 2026
Due Date
Apr 21, 2026
Color Video Pipeline and Sewer Cleaning Equipment
Release: Apr 8, 2026
Close: Apr 21, 2026
Procure new and replacement color video pipeline inspection systems, sewer cleaning units, OEM-certified accessories, and maintenance support. These resources are needed to support sewer line inspection, cleaning, and overall infrastructure asset management operations.
AvailableConstruction of Rural Water System Project – RW1A Pipeline.
Posted Date
Nov 5, 2025
Due Date
May 20, 2026
Raw Water 1A (RW1A) Pipeline Project - RFP
Release: Nov 5, 2025
Close: May 20, 2026
Construction of Rural Water System Project – RW1A Pipeline.
AvailableSeeking to develop a list of pre-commercial energy storage technologies and products to be used as a pipeline for its pre-commercial projects.
Posted Date
Mar 31, 2026
Due Date
Mar 31, 2027
Pre-Commercial Energy Storage Pipeline (Request for Qualifications)
Release: Mar 31, 2026
Close: Mar 31, 2027
Seeking to develop a list of pre-commercial energy storage technologies and products to be used as a pipeline for its pre-commercial projects.
AvailableWork includes 237 SY of asphalt patch; cip, 1 EA of horizontal relocation 5 FT by 5 FT; cip, 8 EA of relocate existing gas meter; cip, 58 LF of customer side plumbing; cip, 5,352 SY of pavement microsurfacing; cip, 38 sf of private walkway; cip, 160 LF of concrete garden wall; cip, 2 EA of tree trimming; compl, 5 EA of tracing wire test box; cip, 2 EA of tree trimming; compl, 160 LF of concrete garden wall; cip, 2,050 SF of drivepad, 6" thick; cip. See attached file.
Posted Date
Mar 27, 2026
Due Date
May 5, 2026
Broadmoor, Galaxy, & Sirius Phmsa Grant Pipeline Rehab
Release: Mar 27, 2026
Close: May 5, 2026
Work includes 237 SY of asphalt patch; cip, 1 EA of horizontal relocation 5 FT by 5 FT; cip, 8 EA of relocate existing gas meter; cip, 58 LF of customer side plumbing; cip, 5,352 SY of pavement microsurfacing; cip, 38 sf of private walkway; cip, 160 LF of concrete garden wall; cip, 2 EA of tree trimming; compl, 5 EA of tracing wire test box; cip, 2 EA of tree trimming; compl, 160 LF of concrete garden wall; cip, 2,050 SF of drivepad, 6" thick; cip. See attached file.
AvailableInternal pipeline cleaning and cctv inspection service.
Posted Date
Apr 8, 2025
Due Date
Apr 22, 2026
NR - Internal Pipeline Cleaning and Cctv Inspection - FY26
Release: Apr 8, 2025
Close: Apr 22, 2026
Internal pipeline cleaning and cctv inspection service.
AvailableWin More Pipeline RFPs
Get AI-powered buying signals and real-time alerts for pipeline opportunities