RWCF 60kV Transformer Replacement
Work consists of remove and disconnect an existing 60kv transformer and store on the city's boneyard property; install new city furnished 60kv transformer on existing concrete pad; coordination with manufacturer to install all bushing and fluids; connect primary, secondary, and control wiring; provide substation grounding; provide rental generator(s) to continuously supply 5,000 kw of power throughout the duration of the project and ensure no power interruption.