Cascade Road Underground Cable Replacement RFP
Aug 25, 2026
Closes
Sep 16, 2026
This project involves the replacement of failed underground power cables in an existing six-inch duct. Several new concrete vaults will be added to reduce cable pulling distances. Several existing concrete vaults will be replaced due to asset condition concerns. New sectionalizing cabinets, transformers, or single-phase fuse switchgear will be installed atop the vaults. The six-inch duct will need to be excavated at select locations to be extended into new equipment vaults / enclosures. Replacement of the riser pole at each end of the underground is included in addition to installation of a new mid-span pole to facilitate relocating the single- phase takeoff