Inflow and Infiltration Mitigation Project
Posted
Sep 8, 2026
Oct 6, 2026
Project generally consists of: furnish and install approx. 3,505 LF of 8" DIP and/or 10" HDPE water main and appurtenances installed by open trench method; 15 - 8" and 10" gate valves with valve boxes; 8 hydrant assemblies; 1,092 LF of 3/4" HDPE or copper service pipe, 24 LF 1" HDPE or copper service pipe; 44 - 3/4" corporations, curb stops and boxes; 1 - 1" corporations, curb stops and boxes; and 10 connections to existing water mains; 10 watermain relocations around existing sanitary manholes; replacement of existing sanitary sewer with 3,205 LF of 8" PVC SDR-35; 1,122 LF of 4" and 6" lateral services; 45 connections to existing sanitary sewers; 25 sanitary manhole replacements; 2,396 LF of cured in place relining of existing sanitary sewers; sealing/coating of 7 existing sanitary manholes; restoration of roadways, lawns, miscellaneous surfaces and all disturbed areas.