Special DistrictFL
Posted
Nov 15, 2026
Dec 17, 2026
16-Inch Force Main from Simpson Road to the Parkway Water Reclamation Facility (WRF) RFP
Work inlcudes sewer force main replacement including approximately 1,930 LF of 16" pvc (c900/dr18) force main, 1,580 LF of 20" hdpe (dr-11) force main, and 35 LF of 6" pvc (c900/dr18) force main; removal and abandonment/grouting of existing force main systems (including asbestos cement pipe); connections to existing force mains and stub-outs; associated fittings, valves, and appurtenances; testing and commissioning; site restoration; and all other work.