Fire Life Safety - Inspection, Testing, Maintenance, and Repair Services RFP
Provide fire life safety- inspection, testing, maintenance, and repair services.
Description: Project scope consists of but is not limited to a qualified firm to provide inspection, maintenance, and testing services for existing HVAC life safety dampers (fire, smoke, and combination fire/smoke) in buildings across Westfield State University's campus.
HigherEducation · MA, US
Adjacent opportunities open for bidding right now.
CityCA
Posted
-
Nov 10, 2026
Provide fire life safety- inspection, testing, maintenance, and repair services.
CityMO
Posted
Oct 1, 2026
Oct 30, 2026
Provide fire and life safety systems inspection testing maintenance and repair services.
California Department of General Services
State AgencyCA
Posted
Sep 16, 2026
Nov 4, 2026
Fire life safety system maintenance and repairs for the attorney general building and discovery tree school.
FederalDC
Posted
Oct 28, 2026
Nov 4, 2026
Recreational Safety Boat Testing and Inspection
Decision makers connected to this RFP from Westfield State University.
From the first pre-RFP signals to the published RFP and its files.
Board meeting
608 days before RFP
The FY25 capital plan lists $45,000 for CODE—Fire Damper Study & Testing.
Westfield State University FY25 Capital Plan Spending As of 2/10/25 December Campus Budget Spending FY25 YTD (as of 2/10/25) Reserve Spending FY25 YTD (as of 2/10/25) Total Spending FY25 YTD (as of 2/10/25) Total Unspent (as of 2/10/25) Deferred Maintenance & Project Mgmt 685,019 - - - 685,019 DCAMM Match Projects 685,019 - - - 685,019 Water Main…
Board of Trustees Financial Affairs Committee
Board meeting · Feb 20, 2025
Board meeting
547 days before RFP
The Financial Affairs Committee passed a recommendation to the full Board for a $976,500 preliminary capital budget to begin bidding proposed summer work, including fire-damper study and testing.
o Fire damper study and testing (compliance issue). o Woodward field lighting replacement (phase one). o Scanlon Hall project (critical for minor renovations). Financial Considerations Projects are high priority. Westfield Gas offers about $50,000 a year in incentives. DCAM Energy to identify key energy projects to replace lighting. MOTION made by…
Board of Trustees Financial Affairs Committee
Board meeting · Apr 22, 2025
Board meeting
547 days before RFP
The Financial Affairs Committee proposed another $55,000 for ongoing annual fire-damper code testing and inspections.
FY26 Preliminary Capital Budget Approval April 22, 2025 Overview The University is submitting an early capital budget request to solicit and bid a variety of projects now, for a summer start. State procurement laws and regulations requires that projects are publicly bid and awarded. This process may take 3-6 months before a contract is fully executed. In…
Board meeting
147 days before RFP
Westfield's FY27 funding request carried forward $61,109 for the incomplete Fire Damper Study & Testing project because bid timing required it to roll into FY27.
Westfield State University 5/27/2026 FY27 Funding Request for Incomplete Capital Projects Fund Code Fund Title Org FY26 Total Budget FY26 Total Spending (Includes Encumb. & Reservations) FY26 Remaining Balance Project Complete? Y/N FY27 Request for Unspent Funds Notes on Incomplete Projects 91062 State Project - Ely pool Capital Planning 3,102,968 2,831,463…
RFP published
RFP documents aren’t available here yet.
Our team can help you find the original solicitation documents.
Request File RetrievalProposals due (14 days left)
Board of Trustees Financial Affairs Committee
Board meeting · Apr 22, 2025
3. Fire Damper Study and Testing -- This is an ongoing project. Study and initial funding of $100,000 in FY25 was spent. Another $55,000 is requested for the ongoing annual code requires testing and inspections.
Board of Trustees Meeting Agenda
Board meeting · Apr 22, 2025
Board of Trustees Meeting
Board meeting · May 27, 2026
91476 Fire Damper Study & Testing Capital Planning 100,000 38,891 61,109 N 61,109 Bid timing requires roll into FY27
Westfield State University Board of Trustees Finance Committee Finance Committee Meeting
Board meeting · Apr 13, 2026