Sep 23, 2026
Dec 8, 2026
Description: Rehabilitation of 20 existing bus stops on the west side including new concrete pads, curb and gutter, sidewalks, upgraded curb ramps, replacement of existing benches at select locations, installation of new benches where none currently exist, designated alighting areas, and illuminated bus stop signs
City · CO, US
Decision makers connected to this RFP from City of Pueblo.
Adjacent opportunities open for bidding right now.
CityKS
Posted
Sep 23, 2026
Dec 8, 2026
From the first pre-RFP signals to the published RFP and its files.
Agenda packet
175 days before RFP
The agenda proposed a 2nd RAISE IGA amendment covering approximately 70 ADA-compliant West Side bus-stop rehabilitations and $11,834,725 for Option Phase 1 construction.
Background Paper for Proposed Ordinance COUNCIL MEETING DATE: May 26, 2026 TO: President Mark Aliff and Members of City Council CC: Mayor Heather Graham VIA: Clyde Bishop, City Clerk FROM: Andrew Hayes, Public Works Director SUBJECT: AN ORDINANCE APPROVING A 2ND AMENDMENT TO AN INTERGOVERNMENTAL AGREEMENT BETWEEN THE CITY OF PUEBLO ("CITY"), A COLORADO…
Construction of street crosswalk and bus stops.
Snohomish County Public Transportation Benefit Area Corporation
Special DistrictWA
Posted
Nov 11, 2026
Dec 18, 2026
Improve 23 bus stops across six jurisdictions including clearing and grubbing, sidewalk and pavement removal, pavement restoration, constructing ADA compliant boarding and alighting platforms, bus stop shelter pads, grading, retaining walls up to 5' in height, and landscape restoration.
CityBC
Posted
Oct 16, 2026
Nov 27, 2026
Procurement of services for the integration of bus shelter structures into existing bus stops in Whistler.
Posted
Nov 13, 2026
Dec 10, 2026
Work includes site preparation and grading, erosion control, storm drainage, site utilities, electrical and telecommunications service, asphalt and concrete paving, site lighting, a new restroom building, a pedestrian connector trail, and landscaping.
City Council Regular Meeting
Agenda packet · May 26, 2026
Option Phase 1: Construction of West Side Bus Stop Rehabilitations & Sun Mountain Boulevard Extension $11,834,725 Upon confirmation that all applicable Federal requirements have been met. 3. Approved Project Budget. Eligible Project Costs Base Phase: Preliminary Engineering Option Phase 1: Construction- West Side Bus Stop Rehabilitations & Sun Mountain…
City Council Regular Meeting
Agenda packet · May 26, 2026
Scope: Original list of Bus Stops provided in the RFP came to a total of 70. During early investigations into the list of stops it was determined that 12 of them had recently been improved and therefore did not need additional improvements. City Transit provided a list of 10 stops to be added. As design progressed one of the stops was removed by City…
City Council Regular Meeting
Agenda packet · May 26, 2026
Option Phase 1: West Side Bus Stop Rehabilitations -- implementation of universal design to reconstruct approximately seventy (70) bus stop locations. Work includes: Construction inspection, Landing pad installation, Shelter erection and seating installation, Sidewalk extensions and ADA compliant ramps, Solar Lighting, Wayfinding Signage, and …
City Council Regular Meeting
Agenda packet · May 26, 2026
Agenda packet
175 days before RFP
The source reports earlier City awards to Pinyon Environmental for NEPA services and Bolton & Menk for professional engineering design for the West Side Improvements.
PREVIOUS COUNCIL ACTION: Ordinance 10787 dated September 9, 2024, established Project DT2401, which approved an IGA between the City and FHWA, budgeted and appropriated funds in the amount of $16,834,725.00 for the West Side Connector Project. Resolution 15880 approved on January 27, 2025, awarded a contract to Pinyon Environmental, Inc. for Project No.…
City Council Regular Meeting
Agenda packet · May 26, 2026
Second, 70 West Side bus stops will be rehabilitated to meet ADA standards. The services for these two components were procured in early 2025 and are currently in development.
City Council Regular Meeting
Board meeting · Nov 24, 2025
Board meeting
82 days before RFP
PACOG adopted the Amended FY 2026-2027 UPWP, including transit, pedestrian and bicycle planning and updates to transit route and stop-location data.
CITY is authorized to pre-approved staff from COUNTY to work mutually with CITY staff, and consultants to complete work for transportation planning services, activities, and project execution required of PACOG for planning services and items of work including all labor and materials encompassed within or reasonably necessary to accomplish the assigned tasks…
City Council Regular City Council Meeting
Board meeting · Nov 9, 2026
RFP published
Proposals due (17 days left)