CityVA
Posted
Sep 29, 2026
Oct 29, 2026
CSRM Phase 1A Floodwall Construction - Preload & Wick Drains
The City of Norfolk seeks qualified contractors to install wick drains and perform preload for the Water Street floodwall segment in CSRM Phase 1A. The work is part of a wider flood-protection project co-funded by the U.S. Army Corps of Engineers, and requires electronic bid submission, a 5% bid bond, and 100% performance and payment bonds. The contractor must hold the applicable Virginia license and complete the work within 365 calendar days of the Notice to Proceed; bids are due October 29, 2026, at 4:00 p.m. Eastern.