Indigenous GovernmentNM
Posted
Oct 6, 2026
Nov 19, 2026
Santo Domingo Pueblo Galisteo Lift Station & Force Main RFP
Work consists of installation of new sewer force main from the new lift station to the existing wastewater treatment plant stub out, including open-trench, horizontal directional drill, and jack-and-bore installation, new lift station construction, wet well and valve vault installation, electrical improvements, diversion manhole and valve box installation, and associated force main connections. The work includes approx 7,268 LF of 6" HDPE C-906 DR-17 force main and 1,269 LF of 6" HDPE C-906 DR-11 force main installed using open-trench construction, 1,438 LF of HDPE C-906 DR-11 installed via horizontal directional drilling (HDD), and 286 LF of HDPE C-906 DR-11 in a steel casing installed using jack-and-bore methods