Santo Domingo Pueblo Main Village Lift Station & Force Main RFP
Work consists of installation of new sewer force main from the main village lift station to the lift station, including open-trench and horizontal directional drill installation, wet well rehabilitation, valve vault replacement, electrical improvements, bypass connection, and associated force main connections. This work includes approx 9,668 LF of 6: HDPE C-906 DR-17 force main installed using open-trench construction methods, along with an additional 1,084 LF of HDPE C-906 DR-11 installed via horizontal directional drilling (HDD), removal and replacement of the concrete valve vault and associated components; electrical improvements; installation of a bypass quick-connect to the existing 6-inch force main serving the Main Village Lagoons; and a force main connection to a 45-degree wye at the end of the alignment.