Description: The City’s project calls for expanding the Front Street Lift Station wet well and replacing the station pumps. It includes installing a new 20-inch force main alongside the existing 16-inch main to the wastewater treatment plant. The project records also call for rehabilitating the existing 16-inch force main.
City · MI, US
From the first pre-RFP signals to the published RFP and its files.
Strategic plan
The CIP proposed the Front Street lift-station and force-main upgrade for FY2027, with an estimated 07/1/2026–06/30/2027 schedule and a listed $4.68M budget.
WW - Front St. Lift Station and Forcemain Upgrade Overview Department SEWAGE TREATMENT PLANT Type Capital Improvement Project Number 1001 Estimated Start Date 07/1/2026 Estimated Completion Date 06/30/2027 Project Location Description Recommended in 2022 Tetra Tech lift station engineering analysis; It is recommended to install a new 20-inch diameter…
City of Traverse City Capital Improvements Plan 2026-2032
Strategic plan · 2026
I hereby certify that the above Resolution was adopted by the City Commission on June 1, 2026, at a regular meeting of the City Commission held in the Commission Chambers, Governmental Center, 400 Boardman Avenue, Traverse City, Michigan.
City of Traverse City Annual Operating Budget 2026-2027
Strategic plan · 2026
Agenda packet
38 days before RFP
The City was developing an RFP for the Front Street Lift Station Force Main and Station Upgrade with an estimated cost of $4,680,000.
Front Street Lift Station Force Main and Station Upgrade City is currently developing RFP. $4,680,000.00
City Commission of the City of Traverse City Regular Meeting
Agenda packet · Oct 5, 2026
RFP published
Proposals due (54 days left)
Decision makers connected to this RFP from City of Traverse City.
Adjacent opportunities open for bidding right now.
CityAZ
Posted
Nov 19, 2026
Jan 7, 2027
Work also includes the demolition of select components of the existing lift station, installation of a new wet well and mechanical piping; furnishing and installation of new submersible pumps and motors; construction of a buried hdpe force main; connection to the existing force main; bypass pumping of the existing lift station during construction; replacement of electrical equipment and site lighting; installation of a new entrance gate and cmu wall; a new odor control unit; an emergency eyewash station; a lifting crane; concrete work including reinforcement and formwork; construction of a new site driveway. See attached file.
Special DistrictTX
Posted
-
Dec 8, 2026
Sunfield Municipal Utility District No. 4 is soliciting construction bids for the Satterwhite Subdivision lift station and force main. Bids will be received by Kimley-Horn and Associates, Inc. until 2:00 PM on December 8, 2026. A non-mandatory virtual pre-bid conference will be held via Microsoft Teams at 2:00 PM on November 19, 2026.
CityFL
Posted
Nov 2, 2026
Dec 9, 2026
Work includes 1 LS lift station w-27 upgrades; 1 LS furnish and deliver generator; 1 LS bypass pumping; 85 LF cctv 48" sanitary sewer; 85 LF cipp lining 48" sanitary sewer; 1 LS reconnect rotary park lift station to existing system; 1,600 LF furnish and install 20" ductile iron force main; 30,000 pounds furnish and install ductile iron fittings; 2 EA furnish and install 20" plug valves; 5 EA furnish and install combination air valve assemblies in vaults; 500 LF restrain existing 48" force main; 2,500 LF cap, grout and abandon existing 10", 12" and 20" force mains. See attached file.
CountyFL
Posted
Oct 9, 2026
Dec 3, 2026