Arlington - Phase #17 Sewer and Drain Rehabilitations RFP
Work include installation of approx 68 LF of 8" pvc gravity sewer at one location with up to three building connection; removal and disposal of 68 LF of asbestos cement pipe; replacement of one service wye; installation of two precast concrete sewer manhole; placement of straw wattles and silt sack for environmental protection at one location during construction; 1,268 LF of root treatment; 55 LF of sewer cleaning and inspection of 5" sewer; 1,987 LF of sewer mainline cleaning, inspection, testing and sealing.