Description: The City of Plano seeks low bids to remove and replace approximately 2,300 linear feet of screening wall and sidewalks across four locations in Willow Bend Estates along Legacy Drive. The project is estimated at $2.5 million, and responses are due November 16, 2026, at 2:00 p.m. CT; the posting describes electronic and in-person submission options. The posting lists a sealed solicitation, plan set, and geotechnical report, and requires a bid bond or cashier’s check equal to 5% of the bid amount.
See your top accountsScan your site in seconds. Starbridge identifies your ICP and surfaces emerging opportunities from board meetings, job changes, new grants, contract expirations, RFPs, and more.
From the first pre-RFP signals to the published RFP and its files.
Capital improvement plan
79 days before RFP
The proposed CIP lists removal and replacement of 2,245 linear feet of Legacy Drive screening wall and sidewalks at four Willow Bend Estates locations, with construction funding shown for 2026-27 and 2027-28.
See 4 sourcesHide sources
COMMUNITY INVESTMENT PROGRAM PROJECT NAME START DATE 07/04/2021 ACCOUNT NUMBER 37877 COMPLETION DATE 09/30/2028 PROJECT CODE ENG-S-7463 DESCRIPTION Project includes removal and replacement of 2,245 LF of screening wall and sidewalks in the Willow Bend Estates neighborhood at the following locations: 1. West of Fallkirk Drive on the north side of Legacy…
City of Plano Community Investment Program 2026-2031
COMMUNITY INVESTMENT PROGRAM PROJECT NAME START DATE 07/04/2021 ACCOUNT NUMBER 37877 COMPLETION DATE 09/30/2028 PROJECT CODE ENG-S-7463 DESCRIPTION Project includes removal and replacement of 2,245 LF of screening wall and sidewalks in the Willow Bend Estates neighborhood at the following locations: 1. West of Fallkirk Drive on the north side of Legacy…
PROJECT NAME START DATE 07/04/2021 ACCOUNT NUMBER 37877 COMPLETION DATE 09/30/2028 PROJECT CODE ENG-S-7463 DESCRIPTION Project includes removal and replacement of 2,245 LF of screening wall and sidewalks in the Willow Bend Estates neighborhood at the following locations: 1. West of Fallkirk Drive on the north side of Legacy Drive (180 LF) 2. Fallkirk Drive…
Screening Wall Reconstruction The following projects include the design and construction for the replacement of COP standard brick and mortar screening walls, including foundations, and adjacent sidewalk and alley replacement for various locations in the city. - Screening Wall Replacement -- Hickory Ridge, The Woods of Suncreek, and Independence Pkwy…
The proposed CIP includes a $93,500 screening-wall standard-design study scheduled through September 2027 to optimize construction and life-cycle costs.
See 3 sourcesHide sources
PROJECT NAME START DATE 02/25/2026 ACCOUNT NUMBER 334290 COMPLETION DATE 09/30/2027 PROJECT CODE ENG-S-00031 DESCRIPTION This study provides recommendations to improve City of Plano's screening wall standard design in an effort to optimize the design and reduce construction and life cycle costs. EXPENDITURES PRIOR YEARS RE-ESTIMATE 2026-27 2027-28 2028-29…
City of Plano Community Investment Program 2026-2031
The proposed CIP project lists citywide screening-wall panel reconstruction and related repairs with $2 million in 2027-28, $3 million in 2028-29 and $2 million in 2029-30.
See sourceHide source
COMMUNITY INVESTMENT PROGRAM PROJECT NAME START DATE 10/01/2018 ACCOUNT NUMBER 350006 COMPLETION DATE 09/30/2030 PROJECT CODE PW-S-00010 DESCRIPTION This program will allow for, but is not limited t,o the removal and reconstruction of brick screening wall panels, brick double wall repairs, column reconstruction and mow pad repair. Work will be in various…
City of Plano Community Investment Program 2026-2031
Agenda packet
67 days before RFP
The proposed CIP table lists screening-wall requirements projects with proposed future funding of $5 million for a placeholder and $8 million for Screening Wall Requirements 2027.
COMMUNITY INVESTMENT PROGRAM PROJECT NAME START DATE 02/25/2026 ACCOUNT NUMBER 334290 COMPLETION DATE 09/30/2027 PROJECT CODE ENG-S-00031 DESCRIPTION This study provides recommendations to improve City of Plano's screening wall standard design in an effort to optimize the design and reduce construction and life cycle costs. EXPENDITURES PRIOR YEARS…
Screening Wall Improvements -- Forensic Evaluation & Parametric Study $50,000 Includes funding to complete the forensic evaluation and parametric study that provides recommendations to improve City of Plano's screening wall standard design in an effort to optimize the design and reduce construction and life cycle costs.
The Government of Saskatchewan, through the Provincial Capital Commission, seeks an organization to design, build, and maintain an interactive snow-and-ice playground for the Frost 2027 festival. The structure must include a maze, slides, and professional art carving, with the contractor supplying the necessary snow and ice and maintaining the installation throughout the festival. The contract also includes a smaller youth-programming component, preferably an art activity using winter materials.
Bids are sought from dealerships for sport utility vehicles, establishing a fixed percentage rate above Triple Net Invoice and a per mile delivery rate.
The work includes, but is not limited to, the demolition, removal and replacement of select portions of roofs as well as fluid-applied restoration of select roofs and all associated work.