Discover opportunities months before the RFP drops
Learn more →Retrieving RFP details
Starbridge can help you:
Pain points mentioned in board meetings and strategic plans
Instantly outline and draft all requirements
Bring in your USPs and exploit competitor gaps
Starbridge can help you:
Get ahead of RFPs — target accounts planning budget or ending contracts soon
Accounts with contract expirations, meetings mentioning your product, grants, budget changes and more
Starbridge.ai books 30 - 40% of leads into meetings
Premium
Access the largest public sector contact database
Premium
Get complete source documentation & analysis
Install 18" SLCPP storm pipe and inlets, complete trench repairs, and replace a section of sidewalk. Connection to an existing inlet is also included.
Starbridge can help you:
Pain points mentioned in board meetings and strategic plans
Instantly outline and draft all requirements
Bring in your USPs and exploit competitor gaps
Starbridge can help you:
Get ahead of RFPs — target accounts planning budget or ending contracts soon
Accounts with contract expirations, meetings mentioning your product, grants, budget changes and more
Starbridge.ai books 30 - 40% of leads into meetings
No files attached to this RFP.
Many agencies add documentation later or require FOIA requests. Starbridge can automatically retrieve these files for you.
Storm sewer and roadway improvements.
Posted Date
Dec 22, 2025
Due Date
Jan 15, 2026
Release: Dec 22, 2025
Close: Jan 15, 2026
Storm sewer and roadway improvements.
AvailablePremium
Access the largest public sector contact database
Premium
Get complete source documentation & analysis
Work includes 1 LS clearing and grubbing c; 150 CY topsoil, off-site; 310 ton class i, bedding material, 1" commercial clean stone; 466 ton replacement of unsuitable backfill material, gr 32, (modified subbase pile); 24 LF storm sewer gravity main, trenched, 36" RCP; 24 LF removal of storm sewer; 1 EA pipe apron, 36" rcp; 1 EA footing for concrete pipe apron, 36" RCP; 1 EA pipe apron guard, 36" RCP; 19. 38 VF manhole type, 48" sw-301; 11. 03 VF manhole type, 60" sw-301; 1 EA connection to existing manhole; 7 SY removal of sidewalk; 7 SY pcc, sidewalk, 4" (thickness); 16,439 SF hydraulic - seeding, fertilizing, and mulching, type 1, by sf. See attached file.
Posted Date
Dec 17, 2025
Due Date
Jan 8, 2026
Release: Dec 17, 2025
Close: Jan 8, 2026
Work includes 1 LS clearing and grubbing c; 150 CY topsoil, off-site; 310 ton class i, bedding material, 1" commercial clean stone; 466 ton replacement of unsuitable backfill material, gr 32, (modified subbase pile); 24 LF storm sewer gravity main, trenched, 36" RCP; 24 LF removal of storm sewer; 1 EA pipe apron, 36" rcp; 1 EA footing for concrete pipe apron, 36" RCP; 1 EA pipe apron guard, 36" RCP; 19. 38 VF manhole type, 48" sw-301; 11. 03 VF manhole type, 60" sw-301; 1 EA connection to existing manhole; 7 SY removal of sidewalk; 7 SY pcc, sidewalk, 4" (thickness); 16,439 SF hydraulic - seeding, fertilizing, and mulching, type 1, by sf. See attached file.
AvailableThis project involves a storm sewer replacement. Project to include the removal of existing storm pipe, manholes, inlets, and trees. Installation of the following: SLCPP pipe, 48” 72”, and 84” storm manholes, Type- 4 inlets, and Type-C inlets. Construction activities will include demolition, excavation and minor grading, installation of storm sewer system, lawn and driveway restoration.
Posted Date
Dec 13, 2025
Due Date
Jan 26, 2026
Release: Dec 13, 2025
Close: Jan 26, 2026
This project involves a storm sewer replacement. Project to include the removal of existing storm pipe, manholes, inlets, and trees. Installation of the following: SLCPP pipe, 48” 72”, and 84” storm manholes, Type- 4 inlets, and Type-C inlets. Construction activities will include demolition, excavation and minor grading, installation of storm sewer system, lawn and driveway restoration.
AvailableThe project is for the installation of HDPE pipe via the pipe bursting method of approx. 1,000 LF of existing 8" sewer along the 600 block of Lexington Avenue and 1st Street between Lexington Avenue and Holland Avenue, manhole rehabilitation of three (3) manholes, reconnection and replacement of sewer services and pavement restoration, located in the Avenues subdivision of Cayce.
Posted Date
Dec 19, 2025
Due Date
Jan 27, 2026
Release: Dec 19, 2025
Close: Jan 27, 2026
The project is for the installation of HDPE pipe via the pipe bursting method of approx. 1,000 LF of existing 8" sewer along the 600 block of Lexington Avenue and 1st Street between Lexington Avenue and Holland Avenue, manhole rehabilitation of three (3) manholes, reconnection and replacement of sewer services and pavement restoration, located in the Avenues subdivision of Cayce.
AvailableSurface intent from meeting minutes, budgets, and contract expirations. Influence RFP requirements before competitors ever see them.