Special DistrictLA
Posted
Jun 18, 2025
Nov 12, 2026
Water Production System Improvements, East Well #2 RFP
Project consists of water production system improvements, east well #2. See outside link.
Description: The project involves constructing a new raw water well facility, including installation of the submersible well pump and motor, vertical column discharge piping, above and below grade mechanical piping, valves, meters, fittings, and the connection to the existing raw water main. Additional work includes cast-in-place concrete, chain-link fencing and gates, all required electrical equipment, panels, conduits, and associated components for full facility operation. The project also encompasses site clearing and grubbing, site restoration, tree protection, concrete repair, erosion and sediment control measures, and all other work.
City · FL, US
From the first pre-RFP signals to the published RFP and its files.
Board meeting
571 days before RFP
City officials reported that funds would be moved to prepare for a production well project whose 2026 schedule was pushed back one year.
THAT'S WHERE WE WERE TAKING SOME FUNDS. FUNDS. FUNDS. WHEN FUNDS. WHEN -- FUNDS. WHEN -- IF FUNDS. WHEN -- IF THIS FUNDS. WHEN -- IF THIS WAS FUNDS. WHEN -- IF THIS WAS GOING FUNDS. WHEN -- IF THIS WAS GOING IN WHEN -- IF THIS WAS GOING IN WHEN -- IF THIS WAS GOING IN APRIL, WHEN -- IF THIS WAS GOING IN APRIL, WE WHEN -- IF THIS WAS GOING IN APRIL, WE HAD…
City Commission Regular Meeting
Board meeting · Mar 20, 2025
Board meeting
39 days before RFP
The Commission recorded unanimous passage of the production well drilling services item, with above-ground piping, electrical, controls, and instrumentation still to be bid.
we have one pled which is the 2D on production well drilling services. So just a question or full >> just a couple of questions. I don't need a presentation. So, questions and clarification. $326,000. Is that it? No upgrades of electrical, fencing, lights. We're not have to come back to these people and tell them anymore. Right. >> This is for the actual…
Budget
25 days before RFP
The adopted FY2027 CIP schedules Water Production Well Facilities for bidding in 2026 and construction beginning in FY2027, with $1.3 million budgeted for FY2027.
Water Production Well Facilities Overview Department Utilities & City Engineer Type Capital Improvement Project Number 511801 Strategic Themes Infrastructure, Planning and Growth Description The project scope includes the installation of four new wells and the annual rehabilitation of existing wells as needed. The City operates production wells to supply…
RFP published
RFP documents aren’t available here yet.
Our team can help you find the original solicitation documents.
Request File RetrievalProposals due (16 days left)
City Commission Regular Meeting
Board meeting · Sep 3, 2026
City of Dunedin FY2027 Budget
Budget · Sep 17, 2026
The project scope includes the installation of four new wells and the annual rehabilitation of existing wells as needed. The City operates production wells to supply raw water to the water treatment plant for the production of potable drinking water. Cleaning and rehabilitative activities will be performed on various wells as needed, in addition to locating…
City of Dunedin FY2027 Proposed Budget
Proposed budget · Oct 1, 2026
Decision makers connected to this RFP from City of Dunedin.
Adjacent opportunities open for bidding right now.
Special DistrictLA
Posted
Jun 18, 2025
Nov 12, 2026
Project consists of water production system improvements, east well #2. See outside link.
CityAZ
Posted
Oct 16, 2026
Nov 6, 2026
Work includes 1 EA well sanitation, testing and sampling; 1 EA well pumping analysis and pump tests; 1 EA tank inspections and maintenance; compressor repair and maintenance.
CityCA
Posted
Oct 6, 2026
Nov 12, 2026
The City of Lompoc seeks construction of a 210-foot-deep, 16-inch-diameter stainless-steel potable water supply well. The work includes drilling, developing, and completing the well. It also includes disposal of drill cuttings and development water.
Special DistrictMA
Posted
Oct 14, 2026
Nov 12, 2026
Well 4 replacement well project, including installation of a new well pump and motor, instrumentation and electrical upgrades, and underground piping improvements.