REQUEST FOR QUOTE FOR A WATER MAIN REPLACEMENT
Procurement for the replacement of 1200 LF of 2" PVC water main and the reconnection of twenty-six water services.
Description: Work includes approx 0.1 AC seeding cl 1a; 1,050 LF of 8" water main; 452 SF 5" PCC sidewalk; 5 EA 8" water valves. See outside link.
City · IL, US
Original attachments and procurement documents tied to this bid.
No files attached to this RFP.
Many agencies add documentation later or require FOIA requests. Starbridge can automatically retrieve these files for you.
Request File RetrievalProcurement and program contacts connected to City of DeKalb.
These related opportunities are still open for bidding.
CityNC
Jul 20, 2026
Closes
Aug 28, 2026
Procurement for the replacement of 1200 LF of 2" PVC water main and the reconnection of twenty-six water services.
CityAZ
Jul 29, 2026
Closes
Aug 26, 2026
Project consists of watermain replacement of 10,208 LF of 6 PVC c900 & 540 LF of 8 PVC watermain.
Jersey City Municipal Utilities Authority
Special DistrictNJ
Aug 11, 2026
Closes
Aug 26, 2026
Replacement and installation of 1,044 LF of 12" and 18 LF of 20" cementlined ductile iron water mains, valves, hydrants, fittings, restrained joints, utility crossings and water service connections along Avenue. The project also includes the removal of existing water mains and services, excavation, bedding, backfill, pavement and site restoration, traffic control, and test pits as directed by the Engineer.
CityGA
Jun 1, 2026
Closes
Aug 27, 2026
The project generally consists of the installation of 6,460 LF of 8" ductile iron water main and 480 LF of 6" ductile iron water main, along with the construction of twenty (20) new fire hydrant assemblies and associated appurtenances. Work also includes the transfer of existing water services to the new distribution system, abandonment of obsolete water infrastructure, and restoration of disturbed areas. Roadway improvements include 6,120 SY of concrete pavement replacement and 485 LF of concrete curb and gutter replacement. The project will require implementation and maintenance of erosion and sedimentation control measures throughout construction, including stabilization of disturbed areas, inlet protection, dust control, and other best management practices necessary to comply with applicable permitting requirements. 28 EA 8" gate valve w/box, 1 EA 4'x8' construction sign.