Avenue C Water Main Replacement RFP
Approx. 3000 LF of 8inch Pipe, 500 LF of 6" Pipe. Piping and some fittings are owner supplied materials. Connections to the existing system along each side road.
Description: This work shall include the furnishing of all labor, materials and construction equipment necessary for all excavation and backfill work indicated on the drawings or specified herein. Under this item, the contractor shall install the water mains of the types and sizes as shown on the plans, including all fittings and other appurtenances and the making of all connections. The contractor shall furnish all labor and materials to restore all surface improvements disturbed by his operations as specified herein or under another item or as noted in the drawings. Under this item the contractor shall open trenches and renew water services as shown on the plans or required. Existing services scheduled for renewal shall be disconnected coincident with the installation of the new service leads in a manner which shall reduce the interruption of customer’s water supply to a minimum. Contractor is responsible for providing notification to residents before interruption of water supply occurs.
City · MI, US
From the first pre-RFP signals to the published RFP and its files.
Proposed budget
482 days before RFP
The FY2025-26 proposed budget lists $200,000 for service-line renewals and $325,000 for small water-main construction within a $550,000 water-district capital-improvement programme.
FY2022-23 FY2023-24 2024-25 2024-25 2024-25 2025-26 YEAR END YEAR END ORIGINAL AMENDED ACTIVITY PROPOSED GL NUMBER DESCRIPTION BUDGET BUDGET THRU 2/28/25 EXPENDITURES Dept 549.00 - WATER PLANT CAPITAL IMPROVEMENT 496-549.00-931.000 BUILDING MAINTENANCE 9,788$ 7,980$ 10,000$ 12,000$ 5,626$ 10,000$ 496-549.00-975.583 DAM REPAIRS - ADRIAN & SPRINGVILLE 17,266$…
City of Adrian, Michigan FY2025-26 Proposed Budget
Proposed budget · Jul 1, 2025
Board meeting
189 days before RFP
The proposed FY2026-27 water capital budget lists $150,000 for service line renewals and $600,000 for small water main construction.
2023-24 2024-25 2025-26 2025-26 2025-26 2026-27 YEAR END YEAR END ORIGINAL AMENDED ACTIVITY PROPOSED GL NUMBER DESCRIPTION BUDGET BUDGET THRU 2/28/26 EXPENDITURES 496-549.00-977.528 INSTRUMENTATION & CONTROL 16,805$ -$ 20,000$ 40,000$ -$ 20,000$ 496-549.00-977.XXX HANDRAIL REPLACEMENT -$ -$ -$ -$ -$ 5,000$ 496-549.00-977.XXX ADMIN ROOF REPAIR/REPLACE -$ -$…
Board meeting
175 days before RFP
The City's 25-year Capital Budget addresses looping several dead-end water mains.
• Several "dead-end" water mains need to be looped. These are addressed in the 25-year Capital Budget.
Adrian City Commission Regular Meeting
Board meeting · May 4, 2026
Board meeting
175 days before RFP
The City of Adrian proposed implementing replacement of up to 1,600 water service lines through its DWSRF project plan.
CR26-057 May 4, 2026 RE: UTILITIES -- Authorization to Adopt Final Project Planning Document for Water Service Line Replacements and Designation of Authorized Project Representative RESOLUTION WHEREAS, the City of Adrian recognizes the need to make improvements to its existing wastewater treatment and collection system; and WHEREAS, the City of Adrian…
RFP published
Proposals due (13 days left)
Adrian City Commission Regular Meeting
Board meeting · Apr 20, 2026
496-552.00-975.114 SERVICE LINE RENEWALS 104,465$ 202,175$ 200,000$ 456,650$ 389,347$ 150,000$ 496-552.00-975.576 SMALL WATER MAIN CONSTRUCT 195,620$ 251,096$ 325,000$ 473,217$ 212,836$ 600,000$
City of Adrian FY2026-27 Proposed Budget
Proposed budget · Jul 1, 2026
Adrian City Commission Regular Meeting
Board meeting · May 4, 2026
Decision makers connected to this RFP from City of Adrian.
Adjacent opportunities open for bidding right now.
CityAL
Posted
Oct 27, 2026
Dec 8, 2026
Approx. 3000 LF of 8inch Pipe, 500 LF of 6" Pipe. Piping and some fittings are owner supplied materials. Connections to the existing system along each side road.
CityCA
Posted
Oct 9, 2026
Dec 11, 2026
Water main replacement service.
Posted
Oct 19, 2026
Nov 18, 2026
Construction of ductile iron pipe water main and appurtenances including valves, hydrants, line stops, and connections to existing water system, abandonment of existing water main, new water services and incidental work including seeding and paving replacement.
CityIL
Posted
Oct 2, 2026
Dec 1, 2026
Work includes construction of 8" and 6" water main installed by open cut construction methods, including: pavement removal; trench excavation; water main pipe materials and installation; valves and valve vaults; fire hydrant assemblies including hydrant and auxiliary valve; water service connections; abandonment of existing water main; sanitary sewer removal and replacement; storm sewer removal and replacement; pipe bedding; trench backfill; pavement replacement; driveway replacement; curb and gutter replacement; parkway restoration; traffic control; water main pressure testing and disinfection; and all other work necessary for a complete and functional water main installation as shown, specified, or required.