CityAL
Posted
Oct 27, 2026
Dec 8, 2026
Avenue C Water Main Replacement RFP
Approx. 3000 LF of 8inch Pipe, 500 LF of 6" Pipe. Piping and some fittings are owner supplied materials. Connections to the existing system along each side road.
Description: Construction services to replace the water main along Washtenaw Avenue from S University Avenue to approximately 700 feet south of Tuomy Road.
City · MI, US
Adjacent opportunities open for bidding right now.
CityAL
Posted
Oct 27, 2026
Dec 8, 2026
Approx. 3000 LF of 8inch Pipe, 500 LF of 6" Pipe. Piping and some fittings are owner supplied materials. Connections to the existing system along each side road.
CityIL
Posted
Oct 2, 2026
Dec 1, 2026
Work includes construction of 8" and 6" water main installed by open cut construction methods, including: pavement removal; trench excavation; water main pipe materials and installation; valves and valve vaults; fire hydrant assemblies including hydrant and auxiliary valve; water service connections; abandonment of existing water main; sanitary sewer removal and replacement; storm sewer removal and replacement; pipe bedding; trench backfill; pavement replacement; driveway replacement; curb and gutter replacement; parkway restoration; traffic control; water main pressure testing and disinfection; and all other work necessary for a complete and functional water main installation as shown, specified, or required.
CityIL
Posted
Oct 2, 2026
Dec 1, 2026
Work includes construction of 8" and 6" water main installed by open cut construction methods, including: pavement removal; trench excavation; water main pipe materials and installation; valves and valve vaults; fire hydrant assemblies including hydrant and auxiliary valve; water service connections; abandonment of existing water main; sanitary sewer removal and replacement; storm sewer removal and replacement; pipe bedding; trench backfill; pavement replacement; driveway replacement; curb and gutter replacement; parkway restoration; traffic control; water main pressure testing and disinfection; and all other work necessary for a complete and functional water main installation as shown, specified, or required.
CityIL
Posted
Nov 12, 2026
Dec 1, 2026
Work generally consists of installation of approx., 1270 LF of 12" DI water main using open cut method. This work also includes the removal and/or capping of existing water mains of different sizes, installation of valves, hydrants, and fittings.
Decision makers connected to this RFP from City of Ann Arbor.
From the first pre-RFP signals to the published RFP and its files.
Board meeting
City staff reported that a water-distribution plan update was underway, with recommended system improvements and cost estimates to follow.
2035. Beginning in 2024, we also began a water distribution plan update to identify the needed improvements to the transmission and distribution pipe network, more than 500 miles of pipes underground. This project is anticipated to be complete by the end of this year. The hydraulic model has been updated and is being used to evaluate the distribution system…
Ann Arbor City Planning Commission Regular Meeting
Board meeting · Jun 3, 2025
Um the public services teams are in the process of putting a lot of fine points on what those needs are and they're going to be varied. Uh here we are trying to just at a very high level talk about when we're talking about just plant capacities. So I want to be clear this memo is not talking about distribution systems which is an a detailed analysis that's…
Ann Arbor City Planning Commission
Board meeting · May 6, 2025
Budget
The FY2026 budget lists requested appropriations for Washtenaw Avenue water-main work from South University Avenue to the north end of the Tappan School property.
Request Request Total ProjectID Project Name FY2026 FY2027 FY2028+ FY2026-FY2028+ CITY OF ANN ARBOR Budgeted Capital Improvement Projects By Project Type Requested Project Appropriations for FY2026 UT-ST-26-12 Towner (Dorchester to Canterbury) Stormwater Infiltration 50,000 200,000 200,000 450,000 UT-ST-26-16 Needham, Medford, Buckingham Stormwater…
RFP published
Proposals due (20 days left)
City of Ann Arbor FY2026 Budget
Budget · Jul 1, 2025