Description: The Town of Georgina seeks experienced and qualified vendors to provide construction services for repairs and rehabilitation at various sewage pumping stations. The work addresses deficient building, mechanical, process, access, drainage, and site components. Locations include Sewage Pump Stations 1, 2, 6, 7, 8, 11, 18, and 19.
See your top accountsScan your site in seconds. Starbridge identifies your ICP and surfaces emerging opportunities from board meetings, job changes, new grants, contract expirations, RFPs, and more.
Southwest Delaware County Municipal Authority is soliciting bids for electrical upgrades at its Woodbrook Pump Station. The work also includes SCADA upgrades at the Authority's administration building and pump stations. The successful bidder must furnish performance and payment bonds, each equal to 100% of the contract price.
Work includes electrical upgrades and scada upgrades at the swdcma administration building and pump stations. Contractor shall perform upgrades to the pump station by supplying equipment, materials, and labor to replace the existing pump control panel and vfds with new upgraded equipment including but not limited to a new vfd and harmonic filter, and to install a scada and scada panel in pump station including administration building hardware and administration integration/programming. Work also includes miscellaneous demolition, wet well lighting, mobilization and demobilization, insurance and bonding, and permits. See attached file.
Provide provide professional services for the WRWTP Finished Water Pump Station (FWPS) Upgrades.
RFP documents & timeline
From the first pre-RFP signals to the published RFP and its files.
Budget
The FY2025 budget business case proposed $600,000 for Q1–Q4 2025 construction repairs to Sewage Pump Stations 6, 11, 18, 19 and 23 after completed condition assessments identified necessary repairs and replacements.
See 2 sourcesHide sources
Capital Initiative Business case 25-CI-SEW-04 Title of request: Sewage Pump Station Repairs, Group 2 - Construction Department: Operations and Infrastructure Division: Capital Delivery Budget request: $600,000 Funding Source: Long-term Debt (Water/Wastewater Reserve) Project highlights: What: Repairs to sewage pump stations Why: To ensure asset reliability…
• Construction of rehabilitation of sewage pump stations # 6, 11, 18, 19 and 23 • Construction of repairs to sanitary sewers at various locations throughout Georgina • Construction of a replacement salt and sand storage building at the Egypt Roads Yard
Operations and Infrastructure proposed $350,000 in additional funding to complete sewage pump station rehabilitation during Q2–Q4 2026, supplementing previously funded repairs at SPS 1, 2, 6, 7, 8, 11, 18, 19 and 23.
See 3 sourcesHide sources
2026 Georgina Budget Capital business case 26-CI-SEW-03 Request: Additional funding for sewage pump station facility rehabilitation Department: Operations and Infrastructure Division: Capital Projects Budget request: $350,000 Funding source: Long-term debt (Water/wastewater reserve) Project highlights: What: Request for additional funding to complete the…
RFP published
RFP documents aren’t available here yet.
Our team can help you find the original solicitation documents.
Capital business case 26-CI-SEW-03 Request: Additional funding for sewage pump station facility rehabilitation Department: Operations and Infrastructure Division: Capital Projects Budget request: $350,000 Funding source: Long-term debt (Water/wastewater reserve) Project highlights: What: Request for additional funding to complete the repairs at multiple…