San Francisco International Airport
Special DistrictCA
Jul 29, 2026
Closes
Sep 2, 2026
Runway 19L, 28L & 28R Timber Trestle Improvements
San Francisco International Airport is soliciting sealed bids for design-bid-build safety improvements to the timber trestles serving Runways 19L, 28L, and 28R, which support FAA approach-lighting systems. The work has an estimated construction cost of $13,500,000-$15,700,000, requires a California Class A license, and has a 219-calendar-day contract duration. Bids must be submitted through the Airport's e-Procurement portal by 2:00pm Pacific on September 2, 2026; a virtual pre-bid meeting is scheduled for August 5 and is recommended but not mandatory.