1011 Turk Street Switchboard, UPS2, and HVAC Replacement RFP
Work consists of Replacement of the existing low-voltage switchboards serving the facility, including associated feeder modifications, terminations testing, and commissioning. The work also includes temporary power provisions, phased shutdown sequencing, and cutover coordination to maintain facility operations during construction. HVAC equipment replacement and improvement in the Telecom Room, Server Room, and UPS1 Room. The work includes air duct and AHU modifications, installation of new air circulation between the Server Room and Telecom Room, system integration with the existing BMS, testing, and commissioning; the work also includes power distribution system and HVAC equipment cutover coordination.