Dec 3, 2026
City Bid - Hope Street Culvert Repair
Work include culvert repair.
Description: Construction contract to replace a collapsed culvert across Elm Street in Thomaston, Connecticut with a new concrete culvert structure and perform related incidental and appurtenant work shown in the Contract Documents. The procurement includes furnishing all labor, materials, bonds, insurance and compliance with applicable Federal, State and local regulations including Prevailing Wage requirements and OSHA standards. Bidders must review the Project Manual and Drawings, submit required bid bonds and qualification information, and complete the work within the specified contract period (90 days if feasible, winter shutdown excluded).
City · CT, US
Adjacent opportunities open for bidding right now.
CityCT
Posted
Nov 5, 2026
Dec 3, 2026
Work include culvert repair.
Federal Emergency Management Agency
FederalDC
Posted
Nov 5, 2026
Dec 3, 2026
Repair of the Hope Street culvert.
CityMI
Posted
Sep 23, 2026
Nov 30, 2026
Seeks a development partner to redevelop a 4.38-acre former industrial site in Holly, Michigan, primarily for residential use, with compatible mixed-use concepts also considered.
CityOH
Posted
-
Dec 3, 2026
Work includes street culvert replacement project.
Decision makers connected to this RFP from Town of Thomaston.
From the first pre-RFP signals to the published RFP and its files.
Board meeting
713 days before RFP
First Selectman Mone reported that an approved LoCIP grant would fund Elm Street reconstruction beyond the Town’s $385,000 engineering cost.
6. Selectman's Report E. Mone reported that Thomaston has been approved for a Local Capital Improvement Project (LoCIP) grant for Elm Street reconstruction including sewers, sidewalks, and possibly a bicycle track. The cost to the town will be $385,000 for engineering and the rest will be covered by the grant. He also reported on the Naugatuck Council of…
Thomaston Board of Finance Regular Meeting
Board meeting · Dec 10, 2024
The Town received a LOTCIP grant in the amount of $4M to do Elm Street roadway, drainage, sewer and sidewalk improvements, which will also include a segment of the greenway trail.
Thomaston Board of Selectmen Regular Meeting
Board meeting · Aug 19, 2025
Board meeting
447 days before RFP
The Board of Selectmen moved the Elm Street reconstruction project, with alternative designs, to a town-meeting vote.
The Elm Street project is a reconstruction project that will incorporate a piece of the greenway. It is being funded by Local Transportation Capital Improvement Program (LOTCIP) funds. This project will improve existing sidewalks and pedestrian connectivity, enhance safety of crossing, address storm drainage and ponding issues, improve bicycle and…
Board meeting
433 days before RFP
The Board of Selectmen approved Elm Street Design Alternative 2 and directed the project to proceed to engineering.
Old Business/Discussion re: Potential Town Meeting -- Elm Street LOTCIP Project: At the last meeting of the BOS, two options were proposed Design Alternative Option 1 and Design Alternative 2, both with a greenway trail incorporated. First Selectman Mone said it is potentially possible for both options to be put on the town meeting agenda and for both to be…
Thomaston Board of Selectmen Regular Meeting
RFP published
Proposals due (9 days left)
Thomaston Board of Selectmen Regular Meeting
Board meeting · Sep 2, 2025
Board meeting · Sep 16, 2025