Summary
The City of Austin (Austin Energy) issued IFB 6100 CLMC1105 for construction of a distribution getaway duct bank bore at the East Village substation, including approximately 342 linear feet of 36-inch jack-and-bore with grouted carrier pipes, additional open-cut duct bank runs, and two 12’x12’ manholes. The work includes erosion and sedimentation control and revegetation; Austin Energy will install the conductors after project completion. The solicitation has an estimated value of $1,114,570.00 and requires electronic submission via the City’s eResponse system with compliance plan requirements and multiple posted addenda.