20317/F-R199(350) - Kay's Creek Trail Overpass @ Layton FrontRunner Project

Description: Work consists of new bridge/bridge replacement, includes 79 CY of granular borrow; 110 ft of 4" PVC pipe; 21 ft of 2" PVC pipe; 584 ft of remove fence; remove tree; remove irrigation valve box; 130 SY of remove concrete sidewalk; 52 SY of remove concrete pavement; 24 ft of remove concrete curb and gutter; 123 SY of remove asphalt pavement; 248 CY of roadway excavation; 27 TON of HMA - 1/2"; 47 SY of portland cement concrete pavement 10" thick; 3,185 sf of concrete sidewalk; 307 ft of 8 ft chain link fence, type ii; 230 ft of 5 ft chain link fence, type ii; reconstruct junction box - raise.

Buyer
Released
-
Closes
Oct 6, 2026(19 days left)

Files

Original attachments and procurement documents tied to this bid.