White Lick Creek Trail Extension – Project BE 22327 & CR 150 S Trail West of Dan Jones Road
The project shall consist of placing asphalt trails and associated drainage structures at the project sites.
Description: Work consists of new bridge/bridge replacement, includes 79 CY of granular borrow; 110 ft of 4" PVC pipe; 21 ft of 2" PVC pipe; 584 ft of remove fence; remove tree; remove irrigation valve box; 130 SY of remove concrete sidewalk; 52 SY of remove concrete pavement; 24 ft of remove concrete curb and gutter; 123 SY of remove asphalt pavement; 248 CY of roadway excavation; 27 TON of HMA - 1/2"; 47 SY of portland cement concrete pavement 10" thick; 3,185 sf of concrete sidewalk; 307 ft of 8 ft chain link fence, type ii; 230 ft of 5 ft chain link fence, type ii; reconstruct junction box - raise.
StateAgency · UT, US
Original attachments and procurement documents tied to this bid.
Adjacent opportunities open for bidding right now.
CityIN
Posted
Sep 3, 2026
Sep 21, 2026
The project shall consist of placing asphalt trails and associated drainage structures at the project sites.
Oregon Department of Transportation
State AgencyOR
Posted
Sep 3, 2026
Sep 24, 2026
The Oregon Department of Transportation’s Supplemental Notice to Contractors lists the Beaverton Creek Trail: Westside Trail – SW Hocken Ave Project in Beaverton as a construction solicitation. The project will construct a 1.5-mile, 12-foot-wide regional trail with paving, crosswalk lighting, right-of-way improvements, environmental mitigation, and bicycle and pedestrian amenities. Bids close and open at 9:00 a.m. on September 24, 2026, and the notice is a procurement solicitation rather than a grant-program posting.
CountyCA
Posted
Aug 25, 2026
Oct 6, 2026
Work includes trail and bridge project.
Oregon Department of Transportation
State AgencyOR
Posted
Sep 10, 2026
Oct 1, 2026
Construction of the Trail Creek bridge structure and approach roadway, requiring temporary water management facilities, excavation, reinforcement, prestressed box beams, aggregate base, and painting/striping.
Decision makers connected to this RFP from Utah Department of Transportation.