2026-B4 Bridge Polymer Overlay

Description: Douglas County Project 2026-B4 consists of Shot or sand blasting bridge decks and approach slabs, Placing a Multi-Layer Polymer Concrete Overlay on bridge decks and approach slabs. A contract will be awarded to one bidder. The anticipated “Notice to Proceed” is June 7, 2027. The late “Notice to Proceed” is July 19, 2027. The work is to be completed in 50 working days as per Special Provision 15-DG-108.

Buyer
Douglas County

County · KS, US

Released
Nov 10, 2026
Closes
Dec 1, 2026(19 days left)
See your top accountsScan your site in seconds. Starbridge identifies your ICP and surfaces emerging opportunities from board meetings, job changes, new grants, contract expirations, RFPs, and more.