2024 AMP12 - Cedar Hill SSO Abatement RFP
Aug 14, 2026
Closes
Sep 23, 2026
Upsizing of approx., 2,417 LF of 24" ductile iron pipe to 36" from the planned halls branch diversion structure to just upstream of manhole 1005-030; Installation of eleven 60" diameter precast concrete manholes with transition to 48" diameter riser sections with bolt-down (watertight) manhole frame and cover; installation of approx., 250 LF of 36" cured-in-place pipe lining; Installation of cast-in-place concrete diversion structure with monolithic liner, 24" ductile iron diversion piping, and 72" diameter inside drop manhole with monolithic liner on existing 36-inch diameter ductile iron sewer; Approx., 28 SY of asphalt roadway pavement repair; Site restoration work.