Wastewater Treatment Improvements - Project
Posted
-
Sep 29, 2026
1. 3,749 CY excavation of unsuitable materials or ditch cleaning; 2. 3,899 CY fill material to raise dike and raise eroded areas; 3. 3,500 LF pond dike shaping; 4. 308 LF straw wattles; 5. 1,523 SY erosion control blanket; 6. 2,600 SY of removing and disposing of shrubs and saplings; 7. Remove and dispose of 14 trees; 8. 2,090 tn gravel surfacing; 9. 2 turtle guards on existing structures; 10. 3 pond depth indicators; 11. 142 FT of remove and replace 18" CMP; 12. 210 lf total of triple 36” CMP arch equivalent; 13. 101 LF 12" PVC sanitary sewer; 14. 57 LF 12" dip sanitary sewer; 15. 158 LF post-televising sanitary sewer; 16. Replace 2 manholes; 17. 2 sanitary sewer connections; 18. 5,050 TN rip rap; 19. 3,294 SY fabric filter; 20. 12,230 SY seeding, fertilizing and mulch; 21. 4 tube frame gates; 22. 14 fence signs; 23. Pumping between cells; 24. Replace concrete cover on lift station wet well; 25. Replace electrical conduit for lift station pump.