DESIGN BUILD: construction of a new Water Pollution Control Facility on the BGJWSC's property, offsite effluent discharge piping extension to the receiving water, extension of approx. 2,000 LF of gravity sewer to the proposed plant site, and connection of existing upstream force mains to the gravity sewer system that feeds the plant site. The Project will include the planning, evaluation, design, construction, commissioning, and startup necessary to place the Project in full operation according to contract requirements.
Board meetings and strategic plans from Brunswick-Glynn Joint Water And Sewer Commission
Brunswick Glynn Joint Water and Sewer Commission Commission Meeting
Date: Sep 17, 2026Type: Meeting mention
The Commission discussed several project updates and contract awards. Key topics included the approval of a contract for the Highway 99 water and sewer extension project, the purchase of UV bulbs for the Dunbar Creek plant, and the acquisition of a new polymer system for the Southport wastewater facility. The board also addressed the surplus of a 2012 truck, accepted new infrastructure and easements, and received updates regarding the Golden Isles Parkway force main project, ongoing smoke testing repairs, and the upcoming activation of the Exit 29 well site.
Brunswick-Glynn County Joint Water and Sewer Commission Finance Meeting
Date: Sep 16, 2026Type: Meeting mention
The finance committee meeting covered several key items, including the approval of a contract award for the Highway 99 water and sewer extension project and the purchase of UV bulbs for the Dunar Creek facility. The committee also recommended the purchase of a new polymer system for the Southport wastewater treatment plant and declared an F-150 vehicle as surplus equipment. Additionally, the finance team presented preliminary financial statements for the current fiscal year, discussing revenue trends, operational expenses, and the impact of rising fuel costs on the organization's fleet operations.
Key Contacts
Public-sector contacts connected to Brunswick-Glynn Joint Water And Sewer Commission.
Brunswick-Glynn Joint Water and Sewer Commission Facilities Committee Meeting Minutes
Date: Aug 19, 2026Type: Meeting mention
The Facilities Committee meeting addressed several agenda items, including the final deductive change order for the Community Road Water and Sewer Extension project and contract awards for FY2027 long-term water quality monitoring services, repairs to an HDPE fusion machine, and wind rod replacements at the First Street Elevated Storage Tank. The Committee also discussed the purchase of replacement components for aeration basin mixers at the Academy Creek Water Reclamation Facility and new equipment for remote water distribution pressure monitoring. Additionally, the Committee reviewed requests for the dedication of infrastructure and easements, and received reports on water production, wastewater plant flows, and capital projects.
Extracted from official board minutes, strategic plans, and video transcripts.
Meeting signals
Know what buyers discuss before RFPs drop
Track Brunswick-Glynn Joint Water And Sewer Commission meetings, strategic plans, and budget discussions before the public bid appears.