Task #2 - CMC Industrial Access Road
Posted
Sep 23, 2026
Oct 20, 2026
Priority 1 expectation is to fine grade, install additional drainage structures, and pave approx. 1,800 LF of existing gravel access road to CMC Steel this fall before asphalt plants close. This section also includes a rail crossing and truck turn around area. Priority 2 will be the realignment and widening of approx. 1,300 LF of to relocate the existing entrance, add turn lanes to U.S. 11, and a construct approx. 600 linear of new access road and a new intersection to the new CMC Steel plant. The new entrance location will require utility relocations of 800 LF of 12" and 1,250 LF of 30" ductile iron water line and 210 linear feet of 8-inch SDR-35 sewer line in the road area.