Project consists of furnishing of all labor/ materials and performing all work necessary to the completion of the demolition of the existing pool, pool deck and pool building, and infill. See attached file.
The Town of Madison is seeking bids for qualified abatement and demolition contractors to abate hazardous materials and fully demolish the former Ryerson Elementary School.
From the first pre-RFP signals to the published RFP and its files.
Board meeting
148 days before RFP
The Board approved a land title survey, Phase I environmental assessment, and asbestos inspection for the Allied Mills property.
See sourceHide source
Trusters Carroll and Donley motioned to approve Austin Engineering Company, Inc. for an SPS land title survey in an amount not to exceed $15,000. Ayes: Trustees Woosley, Carroll, Donley, and Zachman. Nays: None. Motion passed. Trustees Donley and Carroll motioned to approve E2 Companies' proposal for a Phase I Environmental Site Assessment (Phase I ESA) in…
Village of Bartonville Board of Trustees Special Meeting Minutes
The Board authorized advertising the former Allied Mills property demolition and asbestos-abatement project, with bids expected to open December 1 and work expected to take approximately two years.
See sourceHide source
Engineer Meyer reviewed a proposed schedule for demolition of the former Allied Mills property. Bid documents are expected to be issued October 1, with bids opened December 1. The work is expected to take approximately two years because of asbestos abatement, demolition, utility coordination, and IDOT approvals. The bid documents will also address crushing…
Village Of Bartonville Board Of Trustees Meeting Minutes