2027 Annual Stormwater Pipe Repair Project
The City of Shawnee is seeking bids for its 2027 stormwater pipe repair project, including excavation, pipe replacement, in-place lining, and surface restoration at multiple locations. The work includes up to 1,640 linear feet of pipe replacement, 23 storm structures, and 1,680 linear feet of pipe lining, plus curb, sidewalk, street, and landscaping restoration. Bids close November 12, 2026; work is anticipated to start around March 2027, with substantial and final completion due within 200 and 230 days, respectively, after the Notice to Proceed.