Special DistrictWA
Posted
-
Nov 17, 2026
TOTE Terminal Pavement Maintenance and Repair (2026) RFP
Work required for this project includes: the grinding and paving of failed asphalt pavement sections throughout the container yard. Grinding shall be performed using mechanical mills to a depth of approx. 2.5". Replacement asphalt shall be placed in a single lift and finished to match the grade and profile of adjacent paved areas. 1 LS mobilization / demobilization; 5,750 SY asphalt grinding / removal; 825 TN 2.5" HMA paving; 1 LS unforeseen conditions.