Special DistrictIA
Posted
Oct 20, 2026
Nov 10, 2026
South Expressway and 13th Street Transmission Main - Gate Valve Procurement RFP
Procurement of 16-inch, 20-inch, and 36-inch gate valves and appurtenances, including delivery to the project site.
Description: Procurement of pipe materials, including ductile iron water main and fittings, for the South Expressway and 13th Street Transmission Main project for Council Bluffs Water Works.
SpecialDistrict · IA, US
Solicitation files and supporting documents for this bid.
RFP documents aren’t available here yet.
Our team can help you find the original solicitation documents.
Request File RetrievalDecision makers connected to this RFP from Council Bluffs Water Works.
Adjacent opportunities open for bidding right now.
Special DistrictIA
Posted
Oct 20, 2026
Nov 10, 2026
Procurement of 16-inch, 20-inch, and 36-inch gate valves and appurtenances, including delivery to the project site.
Massachusetts Department of Transportation
State AgencyMA
Posted
Sep 14, 2026
Nov 10, 2026
Project involves reconstruction of the intersection either by constructing a roundabout or reconstructing and updating the signal control system and lane assignments. The existing condition includes a non-functioning signalized intersection with three lanes.
Harrison County Public Water Supply District 2
Special DistrictMO
Posted
Nov 4, 2026
Dec 2, 2026
The installation of approx. 27,000 LF of 18" (DR 11) HDPE and 36,000 LF of 16" (DR 13.5) HDPE. Construction will include the installation of air release assemblies, valving, directional creek bores, directional highway bores, and system connections.
St Charles County Public Water Supply District 2
Special DistrictMO
Posted
Sep 25, 2026
Nov 19, 2026
The scope of work for the project includes construction of approx. 12,180 LF of 30" DI water main, including approx. 160 LF of 48" steel casing installed by jack-and-bore methods, together with butterfly valves, gate valves, fire hydrants, air relief valves, fittings, connections to the existing water system, and all associated appurtenances, restoration, and incidental work necessary for a complete installation. Also includes 80 LF of 48" steel casing pipe installed by jack and bore methods.