Mountain Regional Water Special Service District
Special DistrictUT
Posted
Oct 16, 2026
Nov 5, 2026
Upper Evergreen Drive Water Line Replacement Project RFP
work includes 1 LS of mobilization; 1 LS of temporary water system; 2,330 LF of 8" dr18 c900 PVC water line including excavation and bedding; 5 EA of connect to existing water mains; 9 EA of 8" gate valve; 5 EA of fire hydrant assembly; 5 EA of salvage ex fire hydrant; 22 EA of 3/4" water service stub and meter vault; 1 EA of 1" water service; 6 EA of reconnect existing meter/service; 2,850 LF of sawcut and asphalt removal for trenches (LF of water line to includes second cut prior to paving; 129 CY of rock excavation (2' deep x 3" wide for 25% of the trench; 2,543 TN of import granular trench backfill; etc, see attached file.