FederalVA
Posted
Oct 28, 2026
Dec 14, 2026
Beam, Structural SPRPA127RZA37 - (Request for Proposals)
9 lot, beam, structural, NSN: 9540015099974.
Description: The Commission seeks a prime consultant to provide professional structural and civil engineering services under a Task Order Agreement (Contract No. C-826A) for projects within the Commission's jurisdiction along approximately 140 miles of the Delaware River. The two-year, as-needed agreement has a not-to-exceed value of $1.0 million and covers a broad scope including bridge inspection, structural design and rehabilitation, roadway and toll plaza design, geotechnical, traffic engineering, construction management, environmental permitting, and staff augmentation. Proposers must meet local office and licensing requirements, comply with the Commission's Contract Compliance Program (25% IBE target or documented Good Faith Efforts), and submit required insurance, conflict-of-interest, rate schedule and qualification forms as specified in the RFP.
SpecialDistrict · PA, US
Adjacent opportunities open for bidding right now.
FederalVA
Posted
Oct 28, 2026
Dec 14, 2026
9 lot, beam, structural, NSN: 9540015099974.
CountyAB
Posted
Nov 13, 2026
Nov 30, 2026
The County of Vermilion River is seeking proposals from qualified professional engineering firms to provide bridge engineering services for a term of three (3) years from 2027 to 2029 inclusive, with an option for annual extension up to two additional years. The successful proponent will enter into a single professional services agreement encompassing all engineering deliverables required to complete the projects as described. These services are expected to span the planning, procurement, maintenance, BIM inspections, construction, and closeout phases of the work along with other work as described in Appendix D of the RFP Document.
Scotch Plains-Fanwood School District
School DistrictNJ
Posted
Oct 25, 2026
Dec 2, 2026
Provide electric to be generated by a solar photovoltaic power system ("PV System") to be installed.
Washington State Department of Transportation
State AgencyWA
Posted
-
Dec 21, 2026
Design, develop, implement, operate, and maintain Roadway Toll Systems (RTS).
Decision makers connected to this RFP from Delaware River Joint Toll Bridge Commission Of Pa And Nj.
From the first pre-RFP signals to the published RFP and its files.
Board meeting
728 days before RFP
IH Engineers was awarded underwater-substructure design, with condition assessments, foundation reports, permitting and preliminary design advancing for needed repairs.
UNDERWATER SUBSTRUCTURE IMPROVEMENTS DESIGN -- ALL REGIONS Design Contract No. C-782A (HDH/SJB) During the 2021 Underwater Inspection, repair and/or rehabilitation needed at bridge substructures below the water level was identified in the reports. IH Engineers, P.C. was awarded this project and given limited notice to proceed August 1, 2023. IH's…
Delaware River Joint Toll Bridge Commission Minutes
Board meeting · Nov 25, 2024
Board meeting
238 days before RFP
The Commission advanced consultant preparation for Route 1 over Route 29 northbound bridge superstructure replacement based on inspection findings.
Commission Staff and Atkins Réalis USA Inc. held several project status meetings. Commission Staff and Atkins Réalis executed a Consultant Agreement Modification for the superstructure replacement of the Route 1 over Route 29 northbound bridge (NJ Route 29 NB Overpass). It is noted that authorization to execute a Consultant Agreement Modification was…
Delaware River Joint Toll Bridge Commission Minutes
Board meeting · Mar 30, 2026
Board meeting
87 days before RFP
The Commission recorded completion of final bid documents for I-78 Main River Bridge cleaning, painting, and related structural repairs.
I-78 TOLL BRIDGE I-78 MAIN RIVER BRIDGE CLEANING AND PAINTING Design Task Order Assignment No. C-802A-2 (IA/MEM) Traffic Planning and Design, Inc (TPD) was provided with Notice to Proceed on March 19, 2026 to develop construction bid documents for repairs too, and the cleaning and painting of, the I-78 Main River Bridges; and, for miscellaneous repairs as…
Delaware River Joint Toll Bridge Commission Regular Monthly Meeting
Board meeting · Sep 28, 2026
Board meeting
56 days before RFP
The Commission recorded ongoing interchange and bridge-replacement design preparation, including expansion of the NJ 29 project to replace its substructure.
Commission Staff and Atkins Réalis USA Inc. held several project status meetings. The Atkins Réalis design team is addressing the PennDOT Cycle 3 Highway Occupancy Permit (HOP) review comments for the Pennsylvania Avenue interchange design. A meeting with PennDOT to discuss comments that require clarification was scheduled. The design team completed a…
RFP published
Proposals due (26 days left)
Commission Staff prepared a Problem Statement for the superstructure replacement of the Route 1 over Route 29 northbound bridge (NJ Route 29 NB Overpass). The initiative for the superstructure replacement is based on recent inspection findings and evaluations. The design development of the superstructure replacement will be based on recent inspection and…
Delaware River Joint Toll Bridge Commission Minutes
Board meeting · Oct 27, 2025
Delaware River Joint Toll Bridge Commission Regular Monthly Meeting
Board meeting · Sep 28, 2026