2027 Public Works Limestone Aggregate - *Re-Bid* RFP
Purchase of limestone aggregate. Includes domestic #610 price per ton and domestic#57 price per ton.
Description: GENERAL WORK DESCRIPTION The work, in general, to be done under this contract consists of removal of concrete flatwork, removal of concrete curb and gutter, cold planning asphalt pavement, constructing sidewalk, constructing curb ramps, constructing curb and gutter, hot mix asphalt pavement, cape sealing, and slurry sealing. FUNDING SOURCE This project is funded with local funds. ENGINEER’S ESTIMATE The Engineer’s Estimate for this Contract is $915,000. CONTRACT TIME Complete the work, excluding plant establishment and permanent erosion control establishment work, within 35 working days. PREBID OUTREACH MEETING No prebid outreach meeting will be held. OBTAINING OR INSPECTING CONTRACT DOCUMENTS The Project Bid Book and Construction Plans may be obtained from the Public Purchase on-line bidding service. Registration is required to use the service. There is no charge to register or obtain bid documents in digital format. Log onto: https://chico.ca.us/Business-and-Development/Request-for-ProposalsQualifications or www.publicpurchase.com Once you have registered, search for the project title identified on the cover of this Bid Book. The Project Bid Book and Construction Plans may be available for viewing at a Contractor’s Exchange. Contact Exchanges directly to inquire about availability. All addenda notifications will be emailed to plan holders by Public Purchase. QUESTIONS REGARDING THE RFP/RFQ All questions and requests for information regarding the project must be submitted through Public Purchase on the project link. Responses to questions will be distributed to plan holders via Public Purchase. Questions and Requests for Information must be submitted five (5) business days prior to bid opening. The purpose of the question period is to clarify legitimate ambiguities in the solicitation documents. The City will respond, at its discretion, to questions that are relevant to the preparation of responsive proposals to the RFP/RFQ. LICENSING REQUIREMENTS At the time the City awards the contract for this project, the Contractor shall possess either a Class A Contractor License or a combination of classes required by the categories and types of work included in this contract. This contract is subject to state contract nondiscrimination and compliance requirements pursuant to Government Code, Section 12990. Contractor shall possess a City of Chico Business License at the time of contract execution. CALIFORNIA PREVAILING WAGES REQUIREMENTS This project requires the payment of prevailing wage rates to be paid to members of each craft or classification performing work on this project. Pursuant to Section 1773 of the Labor Code, the general prevailing wage rates in the county, or counties, in which the work is to be done have been determined by the Director of the California Department of Industrial Relations. A copy of the California State minimum wage rates is not included in the Specifications advertised for Bid. They may be obtained online at: www.dir.ca.gov/DLSR/statistics_research.html The U.S. Department of Transportation (DOT) provides a toll-free “hotline” service to report bid rigging activities. Bid rigging activities can be reported Mondays through Fridays, between 8:00 a.m. and 5:00 p.m., Eastern Time, (800) 424-9071. Anyone with knowledge of possible bid rigging, bidder collusion, or other fraudulent activities should use the “hotline” to report these activities. The “hotline” is part of the DOT’s continuing effort to identify and investigate highway construction contract fraud and abuse and is operated under the direction of the DOT Inspector General. All information will be treated confidentially, and caller anonymity will be respected. REGISTRATION WITH DEPARTMENT OF INDUSTRIAL RELATIONS A Contractor or subcontractor shall not be qualified to bid on, be listed in a bid proposal, subject to the requirements of Section 4104 of the Public Contract Code or engage in the performance of any contract for public work, as defined in this chapter, unless currently registered and qualified to perform public work pursuant to Section 1725.5. It is not a violation of this section for an unregistered contractor to submit a bid that is authorized by Section 7029.1 of the Business and Professions Code or by Section 10164 or 20103.5 of the Public Contract Code, provided the Contractor is registered to perform public work pursuant to Section 1725.5 at the time the contract is awarded. PAYMENT RETENTIONS; SUBSTITUTION OF SECURITIES Five Percent (5%) will be withheld from each progress payment made to the Contractor for work performed and will be held until completion of the work, its acceptance and the expiration of the period provided by law for filing liens by laborers or materialmen. In accordance with the provisions of Section 22300 of the Public Contract Code of the State of California, securities may be substituted for the monies which the City withholds, or the Contractor may request that retention be paid to an escrow agent.
City · CA, US
From the first pre-RFP signals to the published RFP and its files.
Budget
506 days before RFP
The FY2025-26 budget policy authorized the City Manager to request funds with the Proposed Budget for the annual overlay and slurry seal program in the subsequent fiscal year.
E.6. Annual Street Maintenance Program Pre-Budget Authority Because the Final Budget is not adopted until around June, it is not possible to take full advantage of the weather-related construction season in implementing the City's Annual Street Maintenance Program. Therefore, with the submission of the Proposed Budget to the City Council, the City Manager…
City of Chico FY2025-26 Budget
Budget · Jul 1, 2025
Because the Final Budget is not adopted until around June, it is not possible to take full advantage of the weather-related construction season in implementing the City's Annual Street Maintenance Program. Therefore, with the submission of the Proposed Budget to the City Council, the City Manager is authorized to request funds for the annual overlay and…
City of Chico FY2026-27 Budget
Budget · Jul 1, 2026
Board meeting
184 days before RFP
Public Works reported that advance roadway preparation is performed six months to a year before planned slurry-seal capital projects, which may be scheduled one or two years ahead.
moment. Um, our crews actually complete the labor intensive dig outs, crack sealing and surface preparation. We try to do that six months to a year in advance of these capital projects. That's why occasionally around town you'll see. Road like dig outs or crack sealing that happens well in advance and a lot of folks might say hey, is that it? Are you done…
City Council Budget Session Meeting
Board meeting · May 19, 2026
RFP published
Proposals due (23 days left)
Decision makers connected to this RFP from City of Chico.
Adjacent opportunities open for bidding right now.
CountyLA
Posted
Nov 4, 2025
Dec 1, 2026
Purchase of limestone aggregate. Includes domestic #610 price per ton and domestic#57 price per ton.
CountyMO
Posted
Nov 12, 2026
Dec 8, 2026
Work includes 66,844 SY of applying asphalt rejuvenation products on selected streets.
CityNC
Posted
Oct 27, 2026
Nov 23, 2026
Street rehabilitation and preservation, including asphalt milling and paving, pavement repairs, micro surfacing, rejuvenating, crack sealing, ADA improvements, curb and gutter repairs, pavement markings, and tree removal.
CityCA
Posted
Nov 19, 2026
Dec 8, 2026
The procurement is for pavement rehabilitation work for the City of El Segundo, including hot mix asphalt paving on City streets. The scope also includes re-paving a parking lot and concrete sidewalk repairs. The project requires contractors to possess the appropriate California license and comply with local contractor requirements.