Special DistrictNJ
Posted
Aug 30, 2026
Sep 9, 2026
Phase II Environmental Site Assessment (Request For Proposal)
Environmental site assessment will be as follows and will pertain to liberty towers (32 liberty street, newton, new jersey). 1) review completed phase 1 environmental site assessment to determine the extent of the site assessment that is necessary. 2) locate the recs listed in the phase 1. 3) perform a geophysical survey to determine locations of subsurface structures. 4) take soil samples to determine impacted subsurface conditions. 5) investigate groundwater which shall include a well point(s) to determine if recs have impacted the site. 6) prepare a phase ii report summarizing all findings and recommendation per ASTM. 7) coordinate all field work with subcontractors. 8) restore all disturbed areas to their original condition. 9) the phase ii report must satisfy hud s requirement for a rad conversion and be complete in all areas.