Lehigh Carbon Community College
Higher EducationPA
Posted
Oct 26, 2026
Dec 4, 2026
Biotechnology Training Facility RFP
Work includes biotechnology training facility.
Description: Construction of a new second floor within an existing two-story volume of the outfacility building to accommodate a training roomand offices.
City · MS, US
Adjacent opportunities open for bidding right now.
Lehigh Carbon Community College
Higher EducationPA
Posted
Oct 26, 2026
Dec 4, 2026
Work includes biotechnology training facility.
Michigan Department of Technology, Management and Budget
State AgencyMI
Posted
-
Nov 18, 2026
The Michigan Department of Technology, Management and Budget is requesting quotes to expand the IT room at Ionia Correctional Facility. The available notice provides no detailed scope, quantities, or technical specifications, and says bid attachments must be submitted through SIGMA VSS rather than as hard copies. Email submissions may be permitted only with DCD approval and must arrive by the 2:00 p.m. Eastern deadline.
CityIL
Posted
Oct 20, 2026
Nov 4, 2026
The work includes asbestos abatement, demolition, utility disconnections, backfill and restoration, traffic control and protection
CityAZ
Posted
Oct 15, 2026
Nov 12, 2026
Work consist of 112 lf of sawcut existing asphalt, 577 sy of remove and haul off existing asphalt, 3972 sf of concrete for building pad, 1890 sf of concrete surface polish finishing, furnish and install building - metal building, furnish wal for classroom to include drop ceiling.
Decision makers connected to this RFP from City of Oxford.
From the first pre-RFP signals to the published RFP and its files.
Board meeting
292 days before RFP
The Board recorded approval to advertise the OUT Facility Training room project for bids.
Permission to advertise for the OUT Facility Training room. (Mark Levy)8.c. It was moved by Alderman Bailey, seconded by Alderman Smith, to advertise the OUT Facility Training room project. All aldermen present voting aye, Mayor Tannehill declared the motion carried.
City Of Oxford Board Of Aldermen Meeting
Board meeting · Jan 6, 2026
Board meeting
292 days before RFP
The Board recorded approval of Howorth and Associates' architectural services proposal for an OUT Transit Building expansion adding roughly 3,000 square feet on a second floor.
Consider proposal from Hoorth and Associates for architectural services for modifications to the out transit building. >> So Hworth did the original building. They did the second expansion. This is the third expansion. Uh Donna is requesting 300 square foot rough roughly adding a second floor for 300 ft² or 3,000 ft, excuse me. Um the design is not to…
City Of Oxford Board Of Aldermen Meeting
Board meeting · Jan 6, 2026
Board meeting
110 days before RFP
The Board rejected the OUT Training Room bid and approved re-advertising for the project.
7. Regular Agenda: Special Projects 7.a. Request permission to reject the bid for the OUT training room project. (Mark Levy) It was moved by Alderman Huelse, seconded by Alderman Crowe, to reject the bid for the OUT training room project. With all aldermen present voting aye, Mayor Pro-Tem Bailey declared the motion carried. 7.b. Request permission to…
City of Oxford Board of Aldermen Board of Aldermen Meeting
Board meeting · Jul 7, 2026
On June 25th at 1:00 p.m., the City of Oxford received a single bid for the OUT Training Room addition from Williams Construction, LLC in the amount of $355,890.00. The bid exceeds the project budget, and based on the recommendation of the project architect, Jonathan Mattox, staff is requesting that the bid be rejected. Staff recommends rejection of the bid…
City of Oxford Board of Aldermen Regular Meeting
Agenda packet · Jul 7, 2026
>> So, we only received one bid for this project, which is kind of unusual. It's $355,890, which is well over the budget. So, we're asking permission to reject this bid. Have >> a motion. So, move. >> Second. >> All in favor? >> All right. Request permission to revertise for the out training room project. Have a motion. >> So move. >> Second. >> All in…
City of Oxford Board of Aldermen Board of Aldermen Meeting
Board meeting · Jul 7, 2026
Agenda packet
54 days before RFP
The proposed FY 2026–2027 budget lists additional 5339 funds to expand the second-floor level as a facility renovation.
PROPOSED BUDGET 2026 - 2027 County Share University Share Totals 5311 Funds $5,703,120.00 $3,157,074.00 $2,546,046.00 $353,390.34 $353,390.34 $1,839,265.32 Summary by Line items: Total MDOT Local Share City Share Vehicle Budget 3 - 35' Heavy Duty Buses 5339 Funds Local Share City Share County Share University Share Not used in the County $2,966,046.00…
City of Oxford Board of Aldermen Regular Meeting