Summary
Work includes to remove existing sod field, grade and prepare subgrade, and furnish and install new artificial turf field section with associated drainage facilities. 1 LS mobilization / demobilization / erosion control / cleanup; 1 LS remove and abandon ex. Irrigation pipe and sprinklers; 1 LS earthwork (retention pond, dg swale, and backfill); 61,792 SF furnish and install synthetic turf and shock pad ; 61,792 SF drain rock (including under turf section, infiltration trench, around chambers, and swales); 925 LF install PCC curb; 12 EA sc-800 infiltrators; 153 LF 8" perforated pipe; 1 LS contract allowance.