Eastern Municipal Water District
Special DistrictCA
Posted
Aug 26, 2026
Sep 23, 2026
Matthews Transmission Pipeline 1577W RFP
Eastern Municipal Water District is soliciting electronic lump-sum bids for construction of the Matthews Transmission Pipeline 1577W project in Menifee, Riverside County, California, rather than administering a grant program. The scope includes three pressurized potable-water pipelines—the Matthews Pipeline, Watson Pipeline, and Romoland Feeder Extension—and connections to existing systems, including crossings of the Metrolink and SR-74/Caltrans rights-of-way. The opportunity is in the Bidding stage, is estimated at $18–$21 million with a 10% bid bond, and bids are due September 23, 2026, at 10:00 a.m. PDT.