North Dakota Department of Transportation
State AgencyND
Posted
-
Nov 20, 2026
ND 5, JCT I-29 E TO RED RIVER RFP
HMA roadway work on 3.810 miles of ND 5 in Pembina County, from JCT I-29 E to Red River.
Description: Aligning the travel lanes through the intersection, increasing the storage capacity of the turn lanes, and installing lighting on all four approaches.
StateAgency · ID, US
From the first pre-RFP signals to the published RFP and its files.
Board meeting
617 days before RFP
The Idaho Transportation Board approved authority for the US-26/Jct. Hitt Road design agreement, including $190,810 in additional services.
Request to Approve Consultant Agreements. State Design Engineer Monica Crider presented the request for consultant agreement authorization for design and construction engineering and inspection (CE&I) services. The six projects, as shown in the resolution, are District 3, Old Hwy. 30, W. Plymouth Street Bridge, Canyon County by Forsgren Associates; SH- 44,…
Idaho Transportation Board Regular Meeting
Board meeting · Feb 19, 2025
Request to Approve Consultant Agreements. State Design Engineer Monica Crider presented the request for consultant agreement authorization for design and construction engineering and inspection (CE&I) services. The six projects, as shown in the resolution, are District 3, Old Hwy. 30, W. Plymouth Street Bridge, Canyon County by Forsgren Associates; SH- 44,…
Regular Meeting of the Idaho Transportation Board
Board meeting · Mar 20, 2025
Board meeting
196 days before RFP
The Idaho Transportation Board authorized a $34,979 design-services agreement for the US-26, Jct. Hitt Road project.
Request to Approve Consultant Agreements. State Design Engineer Monica Crider presented the request for agreement authorization for design services. The projects, as shown in the resolution, are US-26, Jct. Hitt Road by Horrocks Engineers; SH-55, North Fork Payette River Rainbow Bridge by Modjeski and Masters; and Access to Opportunity, Ada County Highway…
Agenda packet
42 days before RFP
The agenda exhibit listed Key 21923 US 26 Jct Hitt Road (25th East) as a $11,612,000 Safety project moved from FY26 to FY27 after redesign during FY25.
Exhibit 4 FY2026 Projects Rescheduled or Removed from Program to FY2027 AOP = Aquatic Organism Passage SIA = Supporting Infrastructure Assets District Key # Route # Project Name Program Programmed CE/CC/CN Reason 2 23211 SH 14 CASTLE CREEK FISH PASSAGE, IDAHO CO AOP Grant 2,159,500 Grant Funding Hold, Moved to FY26 then to FY27 4 24005 US 93 FY26 HOLLISTER…
Idaho Transportation Board Regular Meeting
Agenda packet · Sep 17, 2026
RFP published
RFP documents aren’t available here yet.
Our team can help you find the original solicitation documents.
Request File RetrievalProposals due (19 days left)
Idaho Transportation Board Regular Meeting
Board meeting · Apr 16, 2026
6 US 26, JCT HITT ROAD (25TH E), BONNEVILLE CO Horrocks, LLC 1/29/2021, Provide Project Development Services. Minor Design changes due to ROW acquisition differences and FHWA office re- evaluating the environmental document for this job is now requiring ITD to provide an (ARDR) Aquatic Resource Delineation Report. Prev: $1,118,995 This: $34,979 Agreement…
Idaho Transportation Board Regular Meeting
Agenda packet · Jun 16, 2026
Decision makers connected to this RFP from Idaho Transportation Department.
Adjacent opportunities open for bidding right now.
North Dakota Department of Transportation
State AgencyND
Posted
-
Nov 20, 2026
HMA roadway work on 3.810 miles of ND 5 in Pembina County, from JCT I-29 E to Red River.
Idaho Transportation Department
State AgencyID
Posted
Oct 13, 2026
Nov 10, 2026
Rehabilitating the existing roadway section, upgrading existing pedestrian ramp facilities to meet ADA requirements, and construct a protected pedestrian crossing with a rectangular rapid flashing beacon.
Kansas Department of Transportation
Special DistrictKS
Posted
-
Nov 18, 2026
Kansas Department of Transportation seeks bids for milling and hot-mix asphalt overlay on 8.972 miles of US-54, from Kingman East CL to the K-14 junction in Kingman County. The contract is Proposal 526112525 (U054-048 KA 8136-01 / ACNHP-A813(601)) and requires completion within 75 contract days, including 55 restricted days. Bids must be submitted electronically through Bid Express by 1:00 p.m. local time on November 18, 2026.
CityOH
Posted
Oct 28, 2026
Nov 19, 2026
Installation of two retaining walls and removal of existing walls/supports along a shared-use path, plus approximately 1,600 feet of asphalt trail resurfacing.