Summary
280 SF plexiglass wind screen panel, 6'x2'-2"; 30 LF wind screen panel mullion, 6' long; 30 LF wind screen panel sill, 4'-6" long; 14 LF bus shelter column; 2 ub bus shelter bench; 1 un type "C'5'x10' non cantilever bus shelter; 100 SF concrete bus shelter pad, 6" thick; 3 UN solar powered light system; 1 un bus stop sign; 23 un inlet repair; 7 un inlet reconstruction; 85 un storm pipe joint sealing; 6 un storm pipe repair; 70 LF remove and replace 24" RCP storm pipe; 35 un curb piece, type "N-ECO"; 35 un bicycle safe grate; 17 SY topsoil spreading, 4" thick; 17 SY fertilizing and seeding; 70 LF remove and replace concrete vertical curb; 6 ton hot mix asphalt 9.5M64 surface course, 2" thick; 11 ton hot mix asphalt 19M64 base course, 5" thick; 44 SY dense graded aggregate base course, 6" thick ; 30 CY soil aggregate, 1-13; 20 SY topsoil stabilization type 2 mat; 5 SY concrete sidewalk, 4" thick ; 650 LF light cleaning existing storm pipe; 50 LF heavy cleaning existing storm pipe.