Description: Furnish and deliver one hundred sixty (160) new, unused Chemical Flow Meters and associated equipment for the Metropolitan Water District of Southern California's Robert A. Skinner Water Treatment Plant, in accordance with Specification ME-5633, Chemical Flowmeter Data Sheets, and Equipment Table. Installation is not included. FOB Destination Delivery Location: METROPOLITAN WATER DISTRICT OF SOUTHERN CALIFORNIA ROBERT A. SKINNER TREATMENT PLANT 33740 BOREL ROAD WINCHESTER, CA 92596 Delivery to Metropolitan must be included in the unit price. Delivery is 90-120 days after receipt of order (ARO) or the best delivery based on factory production schedules and product availability. Bidder will provide the delivery date in the comment section of the specification checklist. Response Packages shall be submitted online through the PlanetBids system. DO NOT SUBMIT A HARDCOPY RESPONSE, OR SUBMIT VIA E-MAIL. Technical Support - In the event you encounter technical difficulties during the uploading process, please contact the Planet Bids, BidsOnline system team as shown below (M-F from 8 a.m. to 5 p.m.): support@planetbids.com or call 818-992-1771, ext. 0. Make sure to read all the terms and conditions of the bid packet and submit all the required documents upon bid submission.
SpecialDistrict · CA, US
From the first pre-RFP signals to the published RFP and its files.
Annual financial report
483 days before RFP
Metropolitan's FY2025 annual report recorded a plan for chemical system rehabilitation at the Robert A. Skinner Plant over the next several years.
Water Treatment Plant Improvements. Metropolitan has five water treatment facilities, which were placed in service from 1941 to 1978. These plants treat water from the CRA and/or the State Water Project and have been subsequently expanded since their original construction. Significant projects will be undertaken over the next several years to maintain the…
The Metropolitan Water District of Southern California Annual Comprehensive Financial Report FY2025
Annual financial report · Jun 30, 2025
Water Treatment Plant Improvements. The F. E. Weymouth Water Treatment Plant, which was placed into service in 1941, is Metropolitan's oldest water treatment facility. Four more water treatment plants were constructed throughout Metropolitan's service area with the Henry J. Mills Water Treatment Plant being the newest water treatment facility, which was…
The Metropolitan Water District of Southern California Board Meeting
Board meeting · Nov 18, 2025
Capital improvement plan
Metropolitan planned to procure and install replacements for all remaining obsolete chemical flow meters at the Skinner plant.
Skinner Plantwide Chemical Flow Meter Replacement The chemical flow meters at the Skinner plant were installed in 2007 with a plant-wide chemical system upgrade and chlorine building construction. The manufacturer no longer supports these flow meters. As a result, replacement parts are no longer available, significantly affecting the staff's ability to…
Metropolitan Water District of Southern California Capital Investment Plan 2026-2028
Capital improvement plan · 2026
Board meeting
195 days before RFP
The Board approved the FY 2026/27 and 2027/28 CIP appropriation and authorized work on projects in the CIP Appendix.
54446 Appropriate $1.025 billion for projects identified in the CIP Appendix for FYs 2026/27 and 2027/28; and authorized the General Manager to initiate or continue work on the capital projects described in the CIP Appendix for FYs 2026/27 and 2027/28, subject to any limits on the General Manager's authority and CEQA requirements (Board Item 8-2). Chair…
The Metropolitan Water District of Southern California Board Meeting
Board meeting · Apr 14, 2026
RFP published
RFP documents aren’t available here yet.
Our team can help you find the original solicitation documents.
Request File RetrievalProposals due (23 days left)
Skinner Plantwide Chemical Flow Meter Replacement The chemical flow meters at the Skinner plant were installed in 2007 with a plant-wide chemical system upgrade and chlorine building construction. The manufacturer no longer supports these flow meters. As a result, replacement parts are no longer available, significantly affecting the staff's ability to…
Engineering, Operations, And Technology Committee Meeting
Agenda packet · Apr 13, 2026
SKINNER FILT PLT, CHLORINE MASS FLOW METERS
Metropolitan Water District of Southern California Capital Investment Plan 2026-2028
Capital improvement plan · Jun 1, 2026
Decision makers connected to this RFP from Metropolitan Water Dist Of Southern California.
Adjacent opportunities open for bidding right now.
Posted
Oct 16, 2026
Nov 17, 2026
Furnish and deliver magnetic flow meters.
Metropolitan Water Dist Of Southern California
Special DistrictCA
Posted
Oct 15, 2026
Nov 19, 2026
Provide removal, hauling, and disposal/recycling of all water treatment process solids (also referred to as sludge) at water treatment plant.
Metropolitan Water Dist Of Southern California
Special DistrictCA
Posted
Nov 3, 2026
Dec 17, 2026
The Metropolitan Water District of Southern California is soliciting bids for the Robert A. Skinner Water Treatment Plant Fire Alarm Control Panels Replacement. The current invitation is numbered 2129A and the buyer-managed listing shows it was posted on November 3, 2026. The solicitation is listed as open for bidding, with bids due December 17, 2026.
East Bay Municipal Utility District
Special DistrictCA
Posted
Oct 1, 2026
Nov 18, 2026
Water treatment plant effluent meters and large customer meters improvements and circle regulator replacement.