CityMO
Posted
-
Dec 4, 2026
Duck Creek Township Box Culvert CR 279 RFP
Replacement of the concrete deck on the box culvert on Stoddard County Road 279, just south of PP Highway.
Description: Work includes replacement of the deck for the box culvert. Remove existing 16x16 concrete top, replace with 16x24 concrete top.
County · MO, US
Adjacent opportunities open for bidding right now.
CityMO
Posted
-
Dec 4, 2026
Replacement of the concrete deck on the box culvert on Stoddard County Road 279, just south of PP Highway.
CountyMO
Posted
-
Dec 4, 2026
Work includes replacement of a box culvert. Remove existing structure, replace with 18x24 structure with wing walls, at height of 7 feet.
Orange Water And Sewer Authority
Special DistrictNC
Posted
Oct 28, 2026
Dec 2, 2026
Cane Creek Culvert Replacements. This project will remove the existing 42” CMP culvert and replace it with a 42” diameter high density polyethylene (HDPE) culvert, 65 LF long, at the location and elevation of the existing culvert. The 42” HDPE culvert will be double wall (smooth interior, corrugated exterior) with integral bell and gasketed spigot joints. This project will remove the existing double barrel 48” CMP culvert and replace it with two 48” diameter high density polyethylene (HDPE) culverts, 60 LF long, at the location and elevation of the existing culvert.
CountyGA
Posted
Nov 2, 2026
Nov 30, 2026
Provide grading, drainage, erosion control, concrete, asphalt paving, and other items necessary for installing a pre-engineered box culvert dip-galv 08ga.
Decision makers connected to this RFP from Stoddard County.
From the first pre-RFP signals to the published RFP and its files.
Board meeting
The commission approved obligating $29,251.50 in LATCF funds toward building and maintaining bridges in Stoddard County.
Commissioner Jarrell makes a motion to approve the obligation of $29,251.50 from the Local Assistance and Tribal Consistency Funds (LATCF) towards the building and maintenance of bridges in Stoddard County, seconded by Commissioner Stewart. Vote asfollows: Jarrell- Yes, Stewart- Yes, Mathis-Yes. All in favor. Motion carried
County Commission Record
Board meeting · Dec 30, 2024
Board meeting
The commission approved Duck Creek Township seeking bids for a bridge deck on County Road 279, with the township responsible for the specifications.
County Commission Record, Stoddard County, Missouri Monday, June 15, 2026 Present: Greg Mathis, Presiding Commissioner, C.D. Stewart, Associate Commissioner Dist I. Wes Howard, Associate Commissioner, Dist II: BobbyJo Boyles, Deputy Clerk Visitors: Sherman Smith- Dexter Statesman Cecil Weeks- Stoddard County Clerk Larry Sandage- Citizen Doug Lowery- Duck…
Stoddard County Commission County Commission Record
Board meeting · Jun 15, 2026
Duck Creek township reguest funds for removal and replace ment of bridge deck on county rond 279, The head walls were poured 24' but the top is 16'wide making ot more tifficult for larger equipment. Estimated cost of project 1s. 15,000 dollars which includes all reinoval and replacement
Stoddard County Commission County Commission Record
Board meeting · Jun 15, 2026
RFP published
Proposals due (7 days left)