Open RFP

Downtown Streetscape Improvements along 3rd Avenue SW/5th Street SW in the City of Cullman

Description: THE PRINCIPAL ITEMS OF WORK ARE APPROXIMATELY AS FOLLOWS: 459 SQ YD – Concrete Sidewalk and Driveway Removal 1,125 LIN FT – Curb and Gutter Removal 6,926 SQ YD – Crushed Aggregate Base Course 940 SQ YD – Concrete Paving for Sidewalks, Curb Ramps and Driveways 617 LIN FT – Roadway Pipe, Various Sizes 9 EACH – Storm Structures 1,748 LIN FT – Curb and Gutter, Various Types 1 LUMP SUM – Decorative Lighting 147 SQ YD – Brick and Concrete Sidewalks THE ENTIRE PROJECT SHALL BE COMPLETED IN ONE-HUNDRED FIFTY (150) WORKING DAYS.

Buyer
Town of Garden City

City · AL, US

Released
-
Closes
Dec 8, 2026(25 days left)