Description: Qualified Contractors for the complete demolition of the existing county senior center and administration building damaged by Tropical storm Helene, removal and lawful disposal of demolition material, removal of foundations and slabs, utility disconnection and capping, and restoration of the site to a stable grass covered condition.
County · NC, US
From the first pre-RFP signals to the published RFP and its files.
Board meeting
707 days before RFP
Avery County identified the need for an engineer to inspect the Senior Center building.
County Manager Updates -- Phillip Barrier, Jr. Helene Updates Mr. Barrier encouraged the citizens to visit the Avery County government facebook and website for information regarding Hurricane Helene resources. Citizens can continue to call 828-733-8273 for information. There will be a Veterans Assistance Outreach for help with FEMA claims tomorrow at Frank…
Avery County Board of Commissioners Regular Session
Board meeting · Dec 2, 2024
Board meeting
574 days before RFP
The county discussed obtaining architect or engineer estimates, including demolition costs, for the Senior Center and Administration Building.
Jeff Welker with North Carolina Emergency Management explained the FEMA Public Assistance Resiliency Program. The goal of public assistance is to put you back at current codes and standards. They are legally obligated to put you back the way you were prior to the storm. If you are in the floodplain, they have to abide by the new flood plain standards. FEMA…
Board meeting
98 days before RFP
The county submitted the demolition scope for the Administration and Senior Center buildings for Environmental and Historic Preservation review, expected to take 45–90 days.
The scope of work for demolition of the Administration and Senior Center buildings has been submitted. The Environmental and Historic Preservation Agency has to review it, and this takes 45-90 days to hear back from them.
Avery County Board of Commissioners Regular Session
Board meeting · Aug 3, 2026
Board meeting
62 days before RFP
The commissioners voted to begin the demolition process for the Senior Center and Administration Building, and the county manager would prepare a bid package.
At the last board workshop, the commissioners voted to begin the process for demolition of the senior center and administration building. She will be working on a bid package for that project.
Avery County Board of Commissioners Meeting
Board meeting · Sep 8, 2026
RFP published
Proposals due (8 days left)
Avery County Board of Commissioners Board Workshop
Board meeting · Apr 14, 2025
Decision makers connected to this RFP from Avery County.
Adjacent opportunities open for bidding right now.
Federal Emergency Management Agency
FederalDC
Posted
Nov 9, 2026
Nov 30, 2026
Demolition and lawful disposal of the Avery County Senior Center and Administration Building, including foundation and slab removal, utility disconnection and capping, and site restoration to a stable grass-covered condition.
Taylorville Community Unit School District 3
School DistrictIL
Posted
Nov 8, 2026
Nov 24, 2026
Performing arts center building addition - bid package #2.
Division of Facilities Management
State AgencyDE
Posted
Oct 21, 2026
Nov 23, 2026
The project generally consists of the complete demolition and removal of nine (9) existing buildings at the former Plummer Community Corrections Center, including all associated building foundations, footings, concrete slabs, and below-grade building construction. All demolition debris shall be removed from the site and disposed of in accordance with applicable regulations. Existing site utilities shall be disconnected, cut, and permanently capped at or immediately adjacent to each building. Existing site utility distribution systems shall remain in place. All existing site improvements, including asphalt paving, roadways, parking areas, sidewalks, curbing, and perimeter fencing, shall remain and be protected throughout demolition activities. Following demolition, building excavations shall be backfilled and rough graded to provide safe, stable, and properly draining conditions. Comprehensive site grading, paving replacement, landscaping, and site redevelopment are not included in the project scope. Hazardous and regulated material abatement will be completed by others prior to demolition.
Delaware Office of Management and Budget
State AgencyDE
Posted
Oct 21, 2026
Nov 23, 2026
The project generally consists of the complete demolition and removal of nine (9) existing buildings at the former Plummer Community Corrections Center, including all associated building foundations, footings, concrete slabs, and below-grade building construction. All demolition debris shall be removed from the site and disposed of in accordance with applicable regulations.