Special DistrictWA
Aug 12, 2026
Closes
Sep 3, 2026
Wallula Dodd Water System - Raindance-Railex Water Line Extension Phase 2 RFP
The Project includes the following Phase 2 Work: Installation of approx. 2,460 LF of 18" ductile iron water main; 130 LF of 30" steel casing, of which 60 LF is to be installed by jack-and-bore method and 70 LF is to be installed by open trench method; 230 LF of 18 " high density polyethylene water main, of which 130 LF is to be installed inside the new steel casing; three hydrant assemblies; two 18" butterfly valves; 2,690 LF of 2" conduit; junction boxes; gravel surface restoration; hydroseeding; general surface restoration; and other related work.