Summary
Installation of approx. 2,730 LF of 8" Diameter CIPP liner, replacement and raising of 8 manhole frames and covers and the lining of 8 manholes with Sprayroq, by-pass pumping and restoration as shown on the map and as specified. Construction sequence provided hereinafter is general in nature and shall provide the basis of preparation of a detailed construction schedule by Contractor: 1.Install any by-pass pumping equipment. 2.Perform preinstallation cleaning and video documentation. 3. Install CIPP lining system. 4. Replace manhole frames and covers and raise manhole to existing ground surface. 5. Install any by-pass pumping and install Sprayroq lining system in manholes. 6. Site restoration.