Summary
Improvements and retrofits to existing stormwater conveyance, treatment and detention systems. The project includes clearing and grubbing, roadway excavation, stormwater conveyance, stormwater treatment, retrofit of stormwater detention facilities, CIPP lining, paving with HMA, erosion control, curb/gutter, traffic control, and site restoration during construction includes 1,230 LF testing storm sewer pipe, 100 LF solid wall PVC storm sewer pipe 12" diam., 470 LF schedule A storm sewer pipe 12" diam., 1 EA hydrodynamic separator, 350 LF cured in place pipe lining 12" diam., 1 EA abandon existing manhole, 1 LS abandon detention facility central.