Water Tower Painting and Miscellaneous Repair Project (Village Greens) RFP
Description: The structure is a 1,500,000 gallon fluted column elevated water storage tank with a high-water level of 85.5 ft. and a diameter of 86 ft. The work includes: Exterior: Abrasive blast clean to an SSPC-SP6 commercial standard within containment. Apply a four (4) coat zinc epoxy urethane fluoropolymer system. Wet Interior: Abrasive blast clean to an SSPC-SP10 near-white metal standard. Apply a three (3) coat zinc epoxy system. Apply a polyurethane caulk to the roof lap seams. Dry Interior: Abrasive blast clean the spot coating failures throughout to an SSPC-SP6 commercial standard. Apply a spot two (2) coat epoxy system to the prepared surfaces. Pit Piping: Abrasive blast clean to an SSPC-SP6 commercial standard. Apply a two (2) coat epoxy system. Foundation: Abrasive blast clean and apply a two (2) coat epoxy system. Splash Pad: Install a concrete splash pad at the overflow pipe discharge. Cathodic Protection: Install an impressed current cathodic protection system. Repairs: 1)Replace the bowl manway gasket. 2)Install a gasket on the bolted painter’s hatch. 3)Install deflector bars on the fill/draw pipe. 4)Replace the sample tap on the fill/draw pipe. 5)Replace the mud valve. 6)Overflow discharge modification. 7)Install a wet interior ladder. 8)Install a swing gate at the top platform opening. 9)Install a pressure vacuum vent and remove the existing vents. 10)Install a roof handrail with a painter’s railing. 11)Relocate the aviation light to a free-standing mount. 12)Repair damaged electrical junction box. 13)Replace the dry interior light bulbs. 14)Install grounding rods for the structure. 15)Install radar monitoring system. 16)Replace the overhead door.
See your top accountsScan your site in seconds. Starbridge identifies your ICP and surfaces emerging opportunities from board meetings, job changes, new grants, contract expirations, RFPs, and more.
From the first pre-RFP signals to the published RFP and its files.
1 file available
Proposed budget
The FY2026 budget lists $1.6 million for water-tower repainting within the Village's water/sewer improvements program.
See sourceHide source
Nearly $19.7M is budgeted in 2026 for various water/sewer system improvements, including $6.6 M for water main replacements, $2.9M in sanitary sewer lift station rehabilitation, $1.8M in sewer force main rehabilitation, $1.6M in water tower re-painting, $1.5M in sanitary sewer main and manhole rehabilitation, $1.5M in hydrant/valve replacements plus other…
Staff proposed repainting Water Tower 3 at Village Greens in 2027 for $1,600,000.
See sourceHide source
DISCUSSION: For the 2027 budget discussion, Village staff prepared a ten-year capital plan to provide information to the board on the extent of the work performed on our water and sanitary systems. Capital Projects - Years 2027 to 2036 The schedule below shows the Capital Improvement Plan for 2027 to 2036. The summary contains all capital projects except…
The City of Eau Claire seeks bids for all labor, materials, equipment, and related work needed to clean, repair, and paint the Folsom Water Tower at 3120 Old Orchard Road, Eau Claire, WI 54703. The solicitation is an Invitation for Bids, and 5% bid security is required. A mandatory pre-bid conference call is scheduled for November 10, 2026, at 10:00 a.m. CST.
Furnishing and installation of security fencing around three municipal water towers at two locations: The project shall include installation of eight-foot (8') galvanized chain-link security fencing with three-strand barbed wire along the top, secure lockable access gates, necessary posts, hardware, and required security signage.
Qualified, licensed, experienced, and financially responsible painting contractors, construction firms, or general contractors to provide comprehensive exterior buildings painting work for county housing multiple properties.